linking budgeted labour unit with the budgeted material unit

2 replies [Last post]
Fady Hakim
User offline. Last seen 7 years 30 weeks ago. Offline
Joined: 29 Aug 2016
Posts: 3
Groups: None

 can i link the budgeted labour unit with the budgeted material unit so when i change the quantity the labour budgeted changes ?and how?

Replies

Fady Hakim
User offline. Last seen 7 years 30 weeks ago. Offline
Joined: 29 Aug 2016
Posts: 3
Groups: None

thanks for your reply, it's primavers 6

It depends on the software that you use.

It is possible and easy if to use Spider Project.

Please specify the software or ask your question in the corresponding discussion.