P6 Schedule with Budgeted Labor Unit

3 replies [Last post]
siddiq ahmed
User offline. Last seen 2 years 6 weeks ago. Offline
Joined: 1 Apr 2015
Posts: 13
Groups: None

Dear Members;

I need some tips regarding budgeted labor unit in P6 schedule;

Case:

I have a construction project with only one resource loaded (labour) and its assigned to all the activities with the budgeted labour units as per quantity of each activity, now how I can determine the percentage complete at WBS level as P6 calculate the Percentage complete with Budgeted Cost at WBS level.

 

Regards;

Siddiq

Replies

siddiq ahmed
User offline. Last seen 2 years 6 weeks ago. Offline
Joined: 1 Apr 2015
Posts: 13
Groups: None

Deleted posted twice

siddiq ahmed
User offline. Last seen 2 years 6 weeks ago. Offline
Joined: 1 Apr 2015
Posts: 13
Groups: None

Thanks David for your reply..

If you got some time i will send you the XER file and you can take a look at that...

 

Actually the program is made by other planner but now iam supposed to update it and get the status..But when i put activity % to the program nothing is changed at the WBS level...Hope you can understand the case with my broken english.This is my Email ID siddiq.ahmed86@gmail.com if you send me a test mail i will send you the XER

 

Siddiq.

David Kelly
User offline. Last seen 1 year 38 weeks ago. Offline
Joined: 19 Oct 2004
Posts: 630

siddiq,

 

You must assign a cost to the resource, as P6's "Performance % complete" only rolls-up cost, not quantity. Of course if every resource is priced at $1.00 per unit then effectively they are the same thing. The % compete value you want  is Performance % complete for the current schedule ( effectively BCWP) and from the baseline Schedule % complete (effectively BCWS)