Planning, Scheduling & Programming Discussion Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Mon, 2017-05-08 13:40 Permalink this can happen if you import this can happen if you import a p3 project or a ms project into p6. did you use any of these ? You have to chage a setting when importing these types of projects to fix this go to tools global change add up top make under select subject area the sure that is says Activity Resource Assignments Where resource equals non labor then Budgeted Non Labor Units = Budgeted Non Labor Units / 8 to get the 8 in the paramater value select {Custom} then this will giev you teh ability to put a value in there then on the right select change the bottom select committ changes Log in or register to post comments
Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Mon, 2017-05-08 13:40 Permalink this can happen if you import this can happen if you import a p3 project or a ms project into p6. did you use any of these ? You have to chage a setting when importing these types of projects to fix this go to tools global change add up top make under select subject area the sure that is says Activity Resource Assignments Where resource equals non labor then Budgeted Non Labor Units = Budgeted Non Labor Units / 8 to get the 8 in the paramater value select {Custom} then this will giev you teh ability to put a value in there then on the right select change the bottom select committ changes
Member for
16 years 3 monthsthis can happen if you import
this can happen if you import a p3 project or a ms project into p6.
did you use any of these ? You have to chage a setting when importing these types of projects
to fix this go to tools global change
add
up top make under select subject area the sure that is says Activity Resource Assignments
Where resource equals non labor
then Budgeted Non Labor Units = Budgeted Non Labor Units / 8
to get the 8 in the paramater value select {Custom} then this will giev you teh ability to put a value in there
then on the right select change the bottom select committ changes