Budgeted Non Labor Units increasing to 8 times when imported to other computer

Member for

16 years 3 months

this can happen if you import a p3 project or a ms project into p6.

did you use any of these ? You have to chage a setting when importing these types of projects

to fix this go to tools global change

add 

up top make under select subject area the sure that is says Activity Resource Assignments

Where resource equals non labor

then Budgeted Non Labor Units = Budgeted Non Labor Units / 8

to get the 8 in the paramater value select {Custom} then this will giev you teh ability to put a value in there

then on the right select change the bottom select committ changes