Urban Planning

3 replies [Last post]
Ramin Abasy
User offline. Last seen 5 years 37 weeks ago. Offline
Joined: 14 Apr 2012
Posts: 3

Dear All,

I am preparing a schedule for urban design, need you cooperation to advise the project phases that we are using for urban planning

 

Thanks

Ramin

Replies

Mike Testro
User offline. Last seen 5 weeks 6 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Ramin

You obviously know more about the subject than I do so just put things in your programme in the order that they have to be carried out and link them logically - Finish > Start.

Best regards

Mike Testro

Ramin Abasy
User offline. Last seen 5 years 37 weeks ago. Offline
Joined: 14 Apr 2012
Posts: 3

Thanks, 

But it needs also environmental, land clearance, structure plan, development plan and etc, how do we make for these items a project phase.

 

Regards

Ramin

Mike Testro
User offline. Last seen 5 weeks 6 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Ramin

This will do for both design and construction on a green field site.

Survey

Site clearance > take out old services - divert live > clear contamination

Earthworks  > cut fill to profiles

Infrastrure > roads > drains > services > sub stations

Structures in phases

Landscaping > planting > water features

Best regards

Mike Testro