Resource loading for multi-level structure with non-typical floors

Member for

15 years 11 months

Ronn,

There are so many easy ways to load resources but it must comply with what is acceptable with the client/consultant.

You may need the Floor Area of every Floor Level and every Zones too.

 

 

Regards, 

Member for

21 years 7 months

Most software define Material Resources as Consumable [nonrenewable] Resources, these are different from renewable resources and also different to volume of work functionalities.

If you are looking to model volume of work beware that resources are a different functionality not intended to mimic volume of work.

In Spider Project we have:

Resources are skilled human resources, equipment, services, supplies, commodities, materiel, budgets, or funds. Resources are used to perform activities in the project. There are resources of renewable and non-renewable type. Renewable resources are resources available to be used after they have already been used on activity. For example, grader, crane, worker or driver. These resources are called Resources in Spider Project.

Non-renewable resources are resources that can be used on one activity. For example, bricks, concrete, energy. These resources are called Materials in Spider Project.

Volume – field for the activity volume (set activity volume in those units that will be used to measure activity execution).

BQ quantities display Volume.

Semantics can be tricky.

If you want to model Volume of Work in software that lacks this functionality I suggest using UDF [user-defined-fields] to represent:

  • To date volume of work
  • This period volume of work
  • Prior Periods volume of work
  • Cumulative volume of work
  • Volume of work units

With the use of formulas or global change you will be able to relate volume of work to % complete though you most probably will not be able to get periods performance for individual prior periods.

Another rudimentary approach can be to use Cost Accounts for each cunrrency unit to represent one volume of work unit. Kind of lacing your right shoe with left foot on a table and right foot on the floor.

The best way is if the functionality is embedded within the software along with much added functionality as this is just the start of it.

Member for

19 years 10 months

Hi Ronn

A simple way to apply global quantities to different floor sizes is to just pro rata the quantity to the square m area of eacch level.

It is rough and ready for floor slabs but you may need to refine it for columns by number per slab.

For external walls it is relatively simple to just measure the extremity and pro rata the total.

Best regards

Mike Testro