Resource/Cost Loading in P3 based on LS and LF

4 replies [Last post]
Louie Ducut
User offline. Last seen 4 years 42 weeks ago. Offline
Joined: 3 Dec 2003
Posts: 3
I want to make a tabular report for the cost and resource loading based on late start and late finish. Can somebody help me.

Replies

Forum Guest
User offline. Last seen 2 years 28 weeks ago. Offline
Joined: 28 Jan 2009
Posts: 1
Groups: None
thanks so much Michael, that’s correct, because I’ve asked the Primavera System and they answer the same.

Good luck.

Louie
Michael Byrne
User offline. Last seen 19 years 36 weeks ago. Offline
Joined: 13 Nov 2003
Posts: 6
Groups: None
Louie,

I have experienced these problems before in trying to develop late data curves through dumping my data into excel. What I found to work, was to create a copy of my schedule offline (call it LATE or whatever you want), and then run a global change changing all of the early starts to late starts, and all of the early finishes to late finishes. Then simply run your reports as normal (early data is now late data)

Good Luck,

Michael
Forum Guest
User offline. Last seen 2 years 28 weeks ago. Offline
Joined: 28 Jan 2009
Posts: 1
Groups: None
Salamat kabayan...
Zq qz
User offline. Last seen 12 years 15 weeks ago. Offline
Joined: 6 Jun 2003
Posts: 163
Groups: None
kABAYAN,
JUST GO TO THE FF MENU:
TOOL , TABULAR REPORTS, RESOURCE, TABULAR THEN ADD.....
IN THE TIMESCALE SELECT THE OPTION YOU WANT.