submission and approvals prior to commencement date

2 replies [Last post]
Chris G.
User offline. Last seen 11 years 13 weeks ago. Offline
Joined: 14 Jul 2006
Posts: 28
Groups: None

Dear PP experts,

I am developing a tender programme for a quite complex resort and hotel tower buildings in a tight completion timeframe.

The qusetion is, "Is it contractually acceptable to make any submission and approval request from the Engineer immediately after receiving LOA but prior to obtaining building permit/commencement date to speed-up things, for example enabling work subcon approval to be on board and mobilize immediately, technical documents, QA/QC, HSE, CEMP plan approvals...?"

Hope for your expert guidance.

Regards,

Chris

Replies

Chris G.
User offline. Last seen 11 years 13 weeks ago. Offline
Joined: 14 Jul 2006
Posts: 28
Groups: None

Mr. Mike,

Appreciate your prompt response.

Regards,

Chris

Mike Testro
User offline. Last seen 32 weeks 4 days ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Chris

As soon as you get a LOA - provided it is drafted correctly - then the contract is active so Yes you can hit the deck running.

If the Engineer has not yet been appointed then you have your first grounds for an Eot before you have started.

Best regards