Explain construction project planning bar chart in relation to project cash flow.

1 reply [Last post]
xue shine
User offline. Last seen 12 years 18 weeks ago. Offline
Joined: 17 Dec 2011
Posts: 2
Groups: None

Explain construction project planning bar chart in relation to project cash flow.

 

tq

Replies

Kannan CP
User offline. Last seen 4 weeks 3 days ago. Offline
Joined: 12 Jun 2008
Posts: 290
Groups: None

1. It depends on how you load the cost for each activity in the schedule. Check your BOQ with cost.

2. Discuss with PM, how to distribute the cost to each activities in the schedule

3. After assigning the cost, you can develop the cash flow curve.

 

Regards