S-Curve to Bar Chart

2 replies [Last post]
Alfon Lyndon Joson
User offline. Last seen 7 years 5 weeks ago. Offline
Joined: 28 Mar 2004
Posts: 35
Groups: None
How do you incorporate/show the progress curve to the schedule bar chart??

Replies

Rahmat Hidayat
User offline. Last seen 27 weeks 6 days ago. Offline
Joined: 30 Jul 2002
Posts: 82
In P3 you can utilize Graphic Reports, then select Resource & Cost, and choose format with Curve for Overlay.I think you can also try by copy-paste s-curve from Excel into Ms Project. In short, there are many ways to make overlays, it’s easy and simple.

Regards
Waseem Saber
User offline. Last seen 1 year 33 weeks ago. Offline
Joined: 1 Dec 2004
Posts: 63
Groups: None
hi,

this is a vague question and i am surprised that such a requirement is requested by anybody,anyway the requirment of the s-curve to show on the bar chart format will nullify the very usage of the bar chart, and therefore don;t be misinformed and work as per the ethics.

cheers {.....}