Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Change must end by date

1 reply [Last post]
Dave Scott
User offline. Last seen 12 years 10 weeks ago. Offline
Joined: 13 Dec 2011
Posts: 4
Groups: None

I recently built a schedule in P6 that had an must end by date of July 23, 2012.

Shortly there after, additional work and time was added to the project.

How can I add the 6 extra weeks to my schedule?  I need to move the must end by date out by an additional 6 weeks.

Thanks,

Dave

Replies

Gary Whitehead
User offline. Last seen 4 years 46 weeks ago. Offline

Dave,

 

From Enterprise > Projects, highlight the relevant project.

Then go to View > Show on Bottom > Project Details

Go to the "Dates" tab of the Project Details, and you can ammend your Must Finish By date here.

 

Cheers,

 

G