Changing the Data Date and its Impression on Project Milestones

1 reply [Last post]
Ed Afkham
User offline. Last seen 12 years 12 hours ago. Offline
Joined: 15 Aug 2011
Posts: 7
Groups: None

 

Changing the data date shouldn’t practically push back project milestones.

How do you justify that considering the fact that it pushes back not started activities the same period of data date? 

Replies

Forrest Chen
User offline. Last seen 7 years 40 weeks ago. Offline
Joined: 29 Dec 2011
Posts: 10
Groups: None

Hi,

If it is the first activity (normally a start milestone), then you need to give it a contraint as 'start on';

as for other activities, you can either constrain them (not recommended) or logically link them together.

Hope the above helps with you question.