What are the 'must have' Period End Reports (Non Cost / Resources loaded)

1 reply [Last post]
Philip James
User offline. Last seen 37 weeks 4 days ago. Offline
Joined: 20 Mar 2016
Posts: 20
Groups: None

Hi

 

What are the must have period end reports, I would be advised to produce

Currently, I receive our contractors programme, and produce the following reports

1. Full Programme, with Last Period and Baseline Variances

2. Critical Path Layout

3. 4, and 8 week lookahead

4. Milestone Slippage

 

The programme submitted is not cost or resource loaded.

 

Regards

Philip

Replies

Zoltan Palffy
User offline. Last seen 3 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

total float report and a schedule narrative