Does anyone have a sample of a Typical Transmission Line Project Schedule that i can use as a template for a presentation?

Replies

Tanveer Younas
User offline. Last seen 7 years 47 weeks ago. Offline
Joined: 30 Apr 2016
Posts: 2
Groups: None

Can any body send me detail schedule of 132 kv Transmission line? so that i can use it as refrnce.

Aswadimanor Safeie
User offline. Last seen 7 years 10 weeks ago. Offline
Joined: 20 Sep 2010
Posts: 6
Groups: GPC Malaysia

Dear all,

I seek your assistant to help me develop testing & commissioning project schedule for 132kv power transmission line & substations.

Attach my draft schedule for your comment.

If you all need the xer file, please contact me via my email as below;

aswadimanor@gmail.com

 

Thanks & Regards,

2455
132kv_nbwntc_schedule_detail_draft_page_1.jpg

2456
132kv_nbwntc_schedule_detail_draft_page_2.jpg

Mangesh Khuspe
User offline. Last seen 23 weeks 6 days ago. Offline
Joined: 10 Apr 2007
Posts: 162

There are very less activities in transmission tower erections.

For substations they will increase.

 

BOQ will detail out those things.