WBS Query

3 replies [Last post]
Julie Plant
User offline. Last seen 12 years 40 weeks ago. Offline
Joined: 26 Feb 2009
Posts: 5
Groups: None

Hi,

I have a schedule which currently is down to level 21, I have amended my data limits within user preferences in the WBS view, however, when I look in the activity view my colours stop at Level 20.  Does anyone know how I can add a colour to the level 21 within the activity view. 

It is taking my Project Name as a level 1 and could do with it being a Level 0 - Any ideas ??

 

Cheers

 

Julie

Replies

Daniel Limson
User offline. Last seen 4 years 35 weeks ago. Offline
Joined: 13 Oct 2001
Posts: 318
Groups: None

Hi Julie,

You can certainly modify the colour of your choice by clicking the icon "group / Sort" and click at the level you want to change. You can actually customize it according to your colour preference.

Sorry for the late reply as I am quite busy with tendering works.

Best regards,

Daniel

 

Julie Plant
User offline. Last seen 12 years 40 weeks ago. Offline
Joined: 26 Feb 2009
Posts: 5
Groups: None

Hi Daniel

I have done that, however, in the activity view you seem to run out of Colours for the WBS at level 20, just wanted to know if you can amend the colouring systems to add in colours from level 20 onwards.

Cheers

Daniel Limson
User offline. Last seen 4 years 35 weeks ago. Offline
Joined: 13 Oct 2001
Posts: 318
Groups: None

Hi Julie,

Go to Admin and then click "admin preference" go to 'data limits' and modify EPS/WBS limit. I think the default is 20.

Regards,

Daniel