Hi,
I have a schedule which currently is down to level 21, I have amended my data limits within user preferences in the WBS view, however, when I look in the activity view my colours stop at Level 20. Does anyone know how I can add a colour to the level 21 within the activity view.
It is taking my Project Name as a level 1 and could do with it being a Level 0 - Any ideas ??
Cheers