Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Query on cost loading

2 replies [Last post]
Shah. HB
User offline. Last seen 15 weeks 1 day ago. Offline
Joined: 25 Nov 2008
Posts: 773
Hi to all

In a baseline programme ,coat is loaded on the freezed BOQ,how the variation interms of cost is shown in the same programme?

Replies

Shah. HB
User offline. Last seen 15 weeks 1 day ago. Offline
Joined: 25 Nov 2008
Posts: 773
Hi Mike

I got it-thanks
Mike Testro
User offline. Last seen 1 week 5 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418
Hi Shahul

You can have more than 1 cost centre with its own column.

Best regards

Mike Testro