Hammock

7 replies [Last post]
Abhishek Choubey
User offline. Last seen 11 years 50 weeks ago. Offline
Joined: 13 Nov 2010
Posts: 12
Groups: None

Greetings!!

 

Can anybody elucidate about "Hammock"..

 

Regards,

Abhishek

Replies

Gary Whitehead
User offline. Last seen 4 years 47 weeks ago. Offline

Ronald,

 

You're quite right about assigning calendars to hammocks. Not sure where I got that from.

Original post edited.

 

Cheers,

 

G

Ronald Winter
User offline. Last seen 3 years 7 weeks ago. Offline
Joined: 4 Jan 2003
Posts: 928
Groups: None

Gary,

 

You must be thinking of some other product other and Primavera software.  You can assign a calendar to Hammocks in SureTrak, P3, and P6.  In addition, you can have any relationship type that you want in any combination with P6 LOE activities

Rafael Davila
User offline. Last seen 2 hours 25 min ago. Offline
Joined: 1 Mar 2004
Posts: 5229

Essentially the common attribute of Hammocks is that their duration is driven by other activities but every software might have a particular implementation on how they work, some software allows for multiple predecessors either ss or ff with the links having their own calendar independent of the predecessors and successors activities.

I do not make much use of hammock activities as when resource loaded the resources are not leveled. Still hammock activities when needed are very useful. The following example reflects the impact of a delay to an activity whose duration varies in function of the delay. A perfect fit for displaying the effect of duration and costs on prolongation claims. The sample is from an actual claim where the job was delayed by the re-design and relocation of one building at the Owner's request.

Photobucket

Landscape maintenance is part of the original contract to start as soon as needed, 10 calendar days after start of landscaping and finish 30 calendar days after finish of job at project delivery. Note resource calendars can be different but must be compatible with activity calendar, using perhaps different workdays while ss lag calendar is in calendar days as required by watering needs and ff lag calendar is in calendar days as defined by the contract. In this job activities were scheduled using regular workweek as per contract, work on week end is not allowed unless asked on time and some reimbursements are done to pay extra inspection costs. The claim is for the difference between 19,200 and 133,200 in this item alone.

Note that resource B might work on other days but landscape maintenance is to be done only on Thursdays and/or Fridays. Here the activity calendar will determine when can B work on the activity.

What is important is that you realize that when transferring data from one software to another or when analyzing other software the behavior of the hammock might differ. Not all software are created equal, keep this always in mind.

Gary Whitehead
User offline. Last seen 4 years 47 weeks ago. Offline

Hammock is an activity type from P3 which is similar to P6's "Level of Effort" type.

 

There are a couple of differences in that you can't assign a calendar to a hammock, and can only use SS and FF relationships

 

[Edit: You can assign calendars to hammocks. please ignore]

Shah. HB
User offline. Last seen 19 weeks 2 days ago. Offline
Joined: 25 Nov 2008
Posts: 773

Hi

Check the below link

 

http://www.htcprojectcontrols.com/TTB2004-6.pdf

 

Regards

Shahul

Abhishek Choubey
User offline. Last seen 11 years 50 weeks ago. Offline
Joined: 13 Nov 2010
Posts: 12
Groups: None

Gary,

 

i am using P6 and i want to know the significance of term "Hammock"

Gary Whitehead
User offline. Last seen 4 years 47 weeks ago. Offline

Abhishek,

 

What software are you using? and what do you want to know?

 

Cheers,

 

G