difference between Progress override and actual dates

2 replies [Last post]
Amro Ahmed
User offline. Last seen 2 years 35 weeks ago. Offline
Joined: 5 Jan 2009
Posts: 107
Dear colleague,
I would like ask about the accurate difference between progress override and actual dates and also analysis for how primavera calculate both?

Replies

Khuong Do
User offline. Last seen 2 years 16 weeks ago. Offline
Joined: 22 Feb 2010
Posts: 118
Groups: None

Hi,

I wrote an article explaining How does Retained Logic, Progress Override and Actual Dates in Scheduling Options work?

Kindly read it here : https://doduykhuong.wordpress.com/2016/06/08/how-does-retained-logic-progress-override-and-actual-dates-in-scheduling-options-work/

Rodel Marasigan
User offline. Last seen 8 weeks 1 day ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Amro,
Below link is where I show the difference of this options.
What is Actuals in Schedule options Post#2