Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Difference between Retain Logic and Override Progress

73 replies [Last post]
Iyke Nwosu
User offline. Last seen 5 years 10 weeks ago. Offline
Joined: 7 Jun 2017
Posts: 6
Groups: None

Dear Distinguised Planners,

Please what is the difference between Retained logic and Progress Override in the scheduling option in P6..

 

Regards

Iyke

Replies

@ Dr. Paul,

[VL] We used soft logic for one purpose: to determine the direction of work and compare the results of different ways. To build the pipeline from the point A to point B or vice versa?

[PDG] As a "hard money contractor" where my own money is on the line if the project succeeds or fails, we use the soft logic to allocate and level resources 2 - 4 weeks in advance. (One week back, 3 Week Look Ahead schedules)

 [VL] Look ahead for three weeks is not sufficient in many projects. We always schedule the whole project with detailed data on those works that are supported by ready drawings and estimates for other works. The aim is to optimize overall schedule and it may determine activity priorities for current jobs. We try to avoid soft links and use resource constrained scheduling optimizing the order of works. The computer estimates more options and creates better schedules than people.

 

[VL] I suggest to get an approval from superintendents for schedules that are used for construction management. 

[PDG] We do not agree with this. There is a HUGE difference between "getting their approval' for a schedule not created by them and forcing the field people to show the scheduler what they plan on doing.  Getting their approval may give them some accountability but what we want them to do is actually plan their work.  The process is what is important, not the schedule itself.

 [VL] Superintendents know that they shall work on approved schedule and it makes them to participate in schedule creation. They do not see the connections of their current work with the future works and so partial optimization may lead for worse overall results. So overall optimization is the responsibility of the scheduler and project manager but the schedule shall take into account all existing constraints and technologies.

 

[VL] When we implemented penalties for superintendent for not reasonable out of sequence execution in one construction company the speed of construction was substantially accelerated. 

 [PDG] We prefer REWARDS rather than PENALTIES. We base interim rewards on SPI and CPI which means the field supers are always looking for ways to OPTIMIZE trade-offs between costs and time.  We do NOT want them looking ONLY at the CPM schedule but also the cost budgets.

 [VL] We used both. At my example we increased superintendents salary by 20% (Reward in advance!) but told them that each case of wrong out of sequence will cost them 10% of their salary and each quality problem discovered in their shift will cost another 10%. So please come to the construction site earlier and accept the work of the previous shift. It was done because we noticed that most quality problems occurred because one shift missed that some jobs of the previous shifts were not finished. The result was tremendous. I am shy to say that the speed of construction was increased by almost 40% (no quality problems, optimized schedule and smooth work with minimal changes). And remember that people were paid not for the time but for volumes of work that were done and everybody became happy.

 

[VL] We usually create and manage three schedules in parallel – optimistic for project team, expected (with required contingency reserves) for project management, “pessimistic” for contract (with additional management reserves). 

[PDG] We do much the same.  We show both early (optimistic) and late date (pessimistic) curves and while we want the field to work towards the Early Date Curve, we also do NOT want them breaching the Late Date Curve (Negative Float) As long as they stay between the ED and LD curves (Leveled or Realistic Curve) we are happy.  Unlike you, most of our clients provide us with UNREALISTIC scheduled completion dates to begin with, so we always show the exact dates the client has asked for in the bid documents, but then practice "defensive scheduling" by loading the schedule with all the owners activities that we know they will be late in delivering, (site access, shop drawing reviews, clarification responses etc) and connecting those activities (using discretionary logic) to near critical path activities.  Then when the owner delays us, (which they almost always do) then we invoke the "but for" defense- "Mr. Owner, "but for" the fact you delayed us, we would have finished on time".  "And now that you've delayed us, we cannot finish per the original contractual dates and now need a change order giving us an extension of time and extended overhead expenses."

[VL] This is usually done when the Owner insists on too aggressive dates. It is risky. We try to involve the Owners in planning but it is not always possible. Including Owner’s activities in the schedule is MUST! The links of Owner activities with the Contractor’s activities are not discretionary. Contractor jobs depend on material supplies, ready to use drawings, permissions, etc.

I always enjoy our debates,

Vladimir

Paul Giamalvo
User offline. Last seen 2 years 38 weeks ago. Offline
Joined: 14 Feb 2011
Posts: 67

@ Vladimir,

OK now I understand better....

 

[VL] We used soft logic for one purpose: to determine the direction of work and compare the results of different ways. To build the pipeline from the point A to point B or vice versa?

[PDG] As a "hard money contractor" where my own money is on the line if the project succeeds or fails, we use the soft logic to allocate and level resources 2 - 4 weeks in advance. (One week back, 3 Week Look Ahead schedules)

 

 

[VL] I suggest to get an approval from superintendents for schedules that are used for construction management. 

[PDG] We do not agree with this. There is a HUGE difference between "getting their approval' for a schedule not created by them and forcing the field people to show the scheduler what they plan on doing.  Getting their approval may give them some accountability but what we want them to do is actually plan their work.  The process is what is important, not the schedule itself.

 

[VL] What you described is impossible if they were involved in planning and understand why certain order of works was selected. 

 

[PDG] Not IMPOSSIBLE.  Yes, it takes more time but in the end, the results are well worth it. To quote the words of General Eisenhower, "plans are useless but planning is essential".  I want to force my field people to think through what their plan is recognizing that it will change, hence the need to fix out of sequence progress.  AND once you've created "Frag Nets" for each superintendent, we have found that updating them doesn't take very long at all and forces the field people to recall what went right and what went wrong and modify their new schedule based on "Lessons Learned".

 

[VL] As I wrote in one of my previous posts out of sequence may happen if the schedule missed something or something happened at the construction site.

[PDG] On that point, we agree 100%.  We KNOW it is going to happen and we don't force our field people to blindly follow the plan.  They are free to make real time decisions, PROVIDED they document what changes they made and why they made them.

 

[VL] When we implemented penalties for superintendent for not reasonable out of sequence execution in one construction company the speed of construction was substantially accelerated. 

 

[PDG] We prefer REWARDS rather than PENALTIES. We base interim rewards on SPI and CPI which means the field supers are always looking for ways to OPTIMIZE trade-offs between costs and time.  We do NOT want them looking ONLY at the CPM schedule but also the cost budgets.

 

[VL] We usually create and manage three schedules in parallel – optimistic for project team, expected (with required contingency reserves) for project management, “pessimistic” for contract (with additional management reserves). 

[PDG] We do much the same.  We show both early (optimistic) and late date (pessimistic) curves and while we want the field to work towards the Early Date Curve, we also do NOT want them breaching the Late Date Curve (Negative Float) As long as they stay between the ED and LD curves (Leveled or Realistic Curve) we are happy.  Unlike you, most of our clients provide us with UNREALISTIC scheduled completion dates to begin with, so we always show the exact dates the client has asked for in the bid documents, but then practice "defensive scheduling" by loading the schedule with all the owners activities that we know they will be late in delivering, (site access, shop drawing reviews, clarification responses etc) and connecting those activities (using discretionary logic) to near critical path activities.  Then when the owner delays us, (which they almost always do) then we invoke the "but for" defense- "Mr. Owner, "but for" the fact you delayed us, we would have finished on time".  "And now that you've delayed us, we cannot finish per the original contractual dates and now need a change order giving us an extension of time and extended overhead expenses."

 

Great debate as always, Vladimir!!!

 

BR,

Dr. PDG, Jakarta

Hi Dr.Paul,

I meant an example in the paper you suggested to read.

“As an example, when elaborating a working plan, one package is the submission of 25 weekly reports, one per week. The plan was that once finished a weekly report the next one could start. What logic is recommended when deliverables have to be submitted with a certain frequency and they depend on one to another?”

Maybe I did not understand this example.

We used soft logic for one purpose: to determine the direction of work and compare the results of different ways. To build the pipeline from the point A to point B or vice versa?

I suggest to get an approval from superintendents for schedules that are used for construction management. What you described is impossible if they were involved in planning and understand why certain order of works was selected. As I wrote in one of my previous posts out of sequence may happen if the schedule missed something or something happened at the construction site.

In any case the reason shall be documented and analyzed. If something was missed the scheduler shall fix the problem and submit new improved work plan. If something happened new situation shall be modelled and new plan created. It is perfect if the changes were made before еруrealization but it is not always possible. Lessons learned help to avoid the errors in the future. But if out of sequence did not have the right reason the superintendent shall be warned and future work shall be done in accordance with the initial plan.

When we implemented penalties for superintendent for not reasonable out of sequence execution in one construction company the speed of construction was substantially accelerated. But by out of sequence we meant the change of work order in the resource constrained schedule. When these penalties were announced superintendents started to pay much more attention to project schedules and out of sequence execution became rare.

Bottom line: If the schedule takes into account all existing constraints, is created and approved with the participance of site personnel, is updated frequently enough out of sequence execution is rare and may teach the company to improve future schedules.

If the schedule was created in the distant office, was not approved by site managers, is very high level and does not take into account some project constraints then it may be used as communication and contract management tool but not for creating reliable work plans and decision making. Out of sequence in such schedules may occur just because they did not take into account some project constraints and so usually the schedules shall be corrected, not the order of work on site.

We usually create and manage three schedules in parallel – optimistic for project team, expected (with required contingency reserves) for project management, “pessimistic” for contract (with additional management reserves). We teach project managers that they manage contingency reserves, the work will not finish before the finish of optimistic schedule. In the project that lasts one year they have much smaller time (like 20 days) for managing risks and uncertainty, for making the project successful. If out of sequence eats project manager’s reserve it is serious and requires special attention. It can eat this reserve directly or by increasing risks and uncertainty in future works.

Best Regards,

VL

Paul Giamalvo
User offline. Last seen 2 years 38 weeks ago. Offline
Joined: 14 Feb 2011
Posts: 67

Hi Vladimir,

I don't understand your comment?  Which paper are you referencing?

 

And by definition, "soft" logic or dependencies is NOT required.  They are voluntary and at least the way I use them, is to allow me (NOT the computer) to allocate my resources using "Rolling Wave" planning.

 

Lastly, I don't get the connection between Weekly reports being sequential and the choice of logic?  According to the GAO's "Best Practices" I can use "soft" logic as long as in my weekly report I disclose I am using it and provide an explanation to support why I used it.

 

The reason I (and many other field people) are so distrustful of CPM schedules is that far too often they are created by schedulers who have little or no real field experience to start with and never bother to take the time to find out how the field plans on executing the work and WHY we have chosen to sequence the work the way we have.  (Often there are field conditions that impact the sequencing of work)  Which is why even if I have worked with our schedulers to create a realistic plan, as a field superintendent or construction project manager, I reserve the right to make changes to that schedule in real time based on what is happening in the field.  Then I expect the scheduler to update the schedule showing what REALLY happened, document why we changed the plan and then let me know what if any, impact that had to the project.

 

I am seeing far too many people here who seem to view the schedule as something that once established, has no flexibility, which is patently false.  A well-done schedule is a living document, subject to modification on the fly.  (Hence "out of sequence progress")  The schedule should have enough contingency built in to cover "normal" risks and the scheduler should be tracking and reporting the consumption of the float or other buffers/contingency.  But many of the postings here seem to support the concept that the scheduler is running the project and the construction PM or Superintendent must follow the schedule?  Ludicrous idea....

 

BR,

Dr. PDG, Jakarta

Dr Paul,

an example in the paper does not require "soft dependencies".

In any case weekly reports shall be created sequentially.

Zoltan Palffy
User offline. Last seen 3 days 14 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

if you look at my example for progress over ride you wil see that it does not work well with hard logic. As soft logic is preferential logic it is sometimes necessary for crew flow but could be challenged. 

Paul Giamalvo
User offline. Last seen 2 years 38 weeks ago. Offline
Joined: 14 Feb 2011
Posts: 67

Given it seems we have thrashed this topic to death, what are everyone's thoughts on the use of Discretionary or "Soft" logic vs using Mandatory or "Hard" Logic?

 

Here is a paper being written by one of my student/clients as part of him qualifying for Guild "Fellow" level.

 

https://pieroanticona-projectcontrol.blogspot.com/2018/09/

 

What do you think?  Good practice or not?

 

BR,

Dr. PDG, Jakarta

Anoon,

you wrote "A scheduler's job in a large organization is really difficult where he/she cannot do anything but just to follow whatever his/her superiors tells them to do."

Yes, when top management does not understand that project schedule reflects the reality and is the decision making tool. Good schedule answers to any what if question and helps to find the best possible way for future improvements. Wise managers don't tell what to do but sit with the scheduler and find what can be done. Unfortunately many managers do not understand this and project schedules are frequently just drawed and this is why the proposals to draw another one but two times shorter are not rare. Without corporate project management culture the schedules will be poor and the schedulers will not have any authority. The schedules become not decision making but communication tools considered as the Guides and nothing more.

Anoon Iimos
User offline. Last seen 2 years 10 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
Vladimir, As you know, "Communications" alone is a huge factor in an international scenario where all documents are in English. A single mistake from a translator for example, can become a disaster especially if it was a misinterpreted decision coming from the top. A scheduler's job in a large organization is really difficult where he/she cannot do anything but just to follow whatever his/her superiors tells them to do. For instance, I had also an ironic experience (from what I'd previously described), where I was responsible for all minutes of site coordination meetings to be written in English (and all project participants were non native English speakers). And of course, I was able to manipulate the minutes sometimes. For example: If someone in the meeting has raised to use "retained logic" only in schedules; I would write in the minutes that: It was discussed and agreed to rectify all out of sequence progress prior to running the next update of the schedule.

Anoon,

that is why I wrote about project management system in the organization.

If it was implemented all projects shall be managed in accordance with the company standards that include methodology, templates, databases of the corporate norms, typical fragment library, etc. Though projects may be unique the ways they are managed shall be standardized. The company manages project portfolio and so projects shall use the same codes, cost components, resource dictionary, etc. The planners shall work within the company and consultants may be invited to help with the complex cases.

These standards may be implemented in companies of any size. Our clients in Russia include construction companies of any size from the largest to smallest. But in Russia contracts require the ways the schedule and progress shall be reported and not the ways project shall be managed as I have seen in some contracts abroad (what software shall be used, what consultants shall be hired, etc.). Such requirements prevent the creation and usage of own project management system.

Anoon Iimos
User offline. Last seen 2 years 10 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
Hi Vladimir, While I agree in everything you said, unfortunately, small and medium size contractors may never have any chance to compete in an international scene. So may just settle for local subcontracting. While the more prominent and top-notch contractors may able to hire several small and medium size subcontractors as well as several consultants (project controls or whatever), and compete for projects wherever they want. And as you know, most (if not all) projects are just one time endeavors and of course always time constrained. Hence, in my opinion, setting up a proper planning or project controls system for a particular project alone is quite impossible to achieve. In fact, I was once hired by a company as a Scheduling consultant for one of their projects somewhere in Africa and was given business class flights, hotel accommodations, buffet food all-day all-night, just for the project, but you know what? I was never allowed or never had any chance to attend site coordination meetings concerning construction, as they just use their own language (no English) during all meetings. So how on earth could you be able to implement what you think is proper construction scheduling? Anyway, who cares if the project is delayed for as long as your account is deposited every month? Yes it's weird but it's a fact.

Anoon,

I agree with most statements in your post:

  1. Construction starts before engineering is finished. And so the horison of detailed planning covers 2-3 months with less detailed schedules of future works (rolling wave planning).
  2. The team on monthly payment may be not interested in acceleration but top management is. And if top management understands the benefits of proper planning, requires and understands proper planning, the system works. That is why I wrote in my previous post that it is easier to implement good project management systems in small and medium size companies.
  3. In Russia it is not rare when construction workers are paid not for the time but for volumes done. When people start to get much more money for proper work they not only understand the value of planning but participate suggesting the better ways to do the work if the planner missed something.

Bottom line: Implementation of good planning and scheduling requires involvement of most interested people and motivation. It works only together with overall project management system implemented in the company. Planning and scheduling is the team work with the scheduler as facilitator and leader.

Anoon Iimos
User offline. Last seen 2 years 10 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
Vladimir, Of course these companies have a high level scheduling in the first place to manage a certain contract, which perhaps using Top-Down approach, because most of contracts abroad were EPC. And before a poor scheduler on site knew anything, the construction has already started, while engineering is in progress or perhaps the GC is still looking for a specialist contractor. So "out of sequence" has occurred even before any detailed planning is done. What you and Dr. Paul have described were (for me) typical Bottom-Up planning for construction, given with complete engineering details. And I guess this never happen in most real construction world (at least from my own experience). Why? Just imagine a "project team" in which all the members were just mere contracted employees of a certain company, with a monthly salary or even a daily rate. Would you think the team would care about proper planning or delays when they cannot make any decision, but just make all kinds of reports?

Anoon,

I believe you and this is sad. I have the same impression talking with the participants of different conferences. There are exceptions but few.

True scheduling works when company owners and top managers understand the value of good planning and what they can loose with poor planning and project control. When they see what money is saved by proper management project planners (we do not have separate term for schedulers) get full support and become powerful figures in project hierarchy. But in any case they are team members and scheduling is the team job. And good planning is easier to implement in small and medium companies where the owners and top managers try to save money. It is hard to implement changes in large companies where people are interested in their jobs but not so much in the results and need to follow methodology created by someone somewhere.

Anoon Iimos
User offline. Last seen 2 years 10 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
Hi Vladimir, Of course I wanted to follow it (if only I can, as a mere employee of a certain company for example). Realities abroad (or outside Russia), at least from my own experience, it is common to find a completely new team for a certain project, when you join a project for example, which can be first time for every one in the team (this is one and very important factor for me). Secondly, most decisions were made or shall come from another continent, in which you got no choice but just to follow. And the list goes on...And ultimately the poor scheduler on site will just do anything he can (even just copying a similar schedule) in order to come out with something to be called a schedule. Just look at most of the questions here in PP, and you might start to believe that what I'm telling are facts.

Hi Anoon,

I described what I have seen in the projects where I participated and which I attended as project management consultant.

You may consider this as an ideal way but it is not unusual in Russia. I found that abroad projects are managed different way - in particular it was strange to me that project scheduler creates project schedule himself without involvement of all project participants that is rare in Russia but common case in other countries. I have made many discoveries that did not anticipate. For example, few contractors abroad level project resources and plan and manage project expenses. Most of our customers work in Russia and their needs, their way of work, their problems are different.

If you think that this is an ideal way why not to follow it?

Anoon Iimos
User offline. Last seen 2 years 10 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
Intruder here..It's nice to read your sentiments about how you describe your own ideal ways of how construction scheduling is supposed to be done properly. Imagine if you two merge together in one project, I can only wonder if which principles or methods shall be followed? Perhaps if you just pay attention to most (if not all) questions posted here in PP (and mostly answered by Zoltan), you might think that what you have intellectually described as how scheduling is supposed to be done were not really happening in the real construction world. The big question is WHY??? FOR now I can only suggest that perhaps you can conduct a survey to as many contractors (only contractors all over the world) as you can and find out exactly how they prepare and implement their construction schedules?

Hi Dr. Paul,

Thank you for your reply.

It looks like we are discussing the same points but keeping in mind different ways of creating and managing project schedule. In our practice schedulers that sit somewhere outside is nonsense. The scheduling is the team work that involves not only scheduler but everybody who is responsible for something (including superintendents). It shall be accepted by everyone and people responsible for different parts of the schedule update them regularly.

An example of work organization on construction site in one Contractor company:

At the beginning of the shift superintendent of the 1st shift enters the numbers of resources (people and machines) that are available (if different than planned), levels the schedule and gets volumes of work that shall be done in his shift.

At the end of the shift he enters the volumes that were actually done and recalculates project schedule creating its next version.

Superintendent of the next shift does the same, etc.

Changing the work order (out of sequence) requires an approval from PM. If done on site without the permission the special report shall be sent to PM with the explanation why it was necessary.

If nothing wrong happened the schedule is analyzed for potential improvements and corrections weekly.

I described the real case that unfortunately is not common. It is also usual that the scheduler sits in the office and collects data from project participants and updates the schedule daily. If no objections or change requests were received the schedule is considered as accepted.

Owners usually update project schedules weekly.

You wrote about YOUR schedule that is not the same as the schedule created somewhere 100 km away. So you use different schedule but it is still project schedule, isn’t it? Then why do you need that original schedule that is useless?

It is common for contractors to manage three schedules in parallel: Contract schedule (do you mean this schedule as created by somebody that is far away?), Project Management Team schedule (that includes necessary contingency reserves) and Work schedule (that is optimistic). Superintendents gets and works with the Work schedule, the scheduler updates all of them.

As for VR and AR you wrote: Imagine the CPM schedule as not being a 2-dimensional piece of paper but a 3-dimensional video showing the workers exactly what work they are supposed to be doing as well as how the work is going to be done? 

Yes, it is nice to show your schedule using VR and AR but first of all it shall be created and optimized. And this is mathematics that cannot be replaced by AR and VR.

Best Regards,

Vladimir

Paul Giamalvo
User offline. Last seen 2 years 38 weeks ago. Offline
Joined: 14 Feb 2011
Posts: 67

Hi Vladimir,

As always, a pleasure to debate you on these issues!!!

1) Why more people outside of Russia don't use Spyder-

You wrote "What shall I answer? The main reason was mentioned in your post: "I only use the CPM schedule as a guide and nothing more."   [PDG] While I agree totally that all schedules should be cost and resource loaded, there is no way that a scheduler sitting in an office 1000 kilometers or 100 kilometers or even 100 meters away can ever understand what is happening on a project right this minute, which is why we end up with so much out of sequence progress in the first place.  This is why I rely on the schedule to enable me to see what MY (not the schedulers) original plan was, updated no more than 12 hours before, with out-of-sequence progress eliminated, to give me a true picture showing where I stand and where I can allocate my available resources to keep making forward progress on the project.  Think of Australian Rules Rugby.  We have a playbook but until your team has the ball, you don't know EXACTLY who will be running with it.

 

2) Multiple WBS Structures- "And about multiple WBS - as you know Spider Project permits to use multiple WBS since its launch in 1993. The number of different structures is not limited. This feature is always used by Spider customers for more that 25 years." 

[PDG] Yes, I agree which is why on TECHNICAL (as opposed to pragmatic) grounds I agree there is no better program than Spyder.  The problem is, I see it as being over-kill because I neither need nor want to be bound or constrained by a CPM schedule that was prepared months ago and maybe only updated a week ago.  I need a real-time status that is no more than 12 hours old, otherwise, it is worthless for me to allocate resources efficiently and effectively, which, as an experienced construction superintendent, I can do much better than any scheduler can, especially when I have an updated schedule, including out of sequence progress fixed, that shows me EXACTLY where I am.

 

3) "As for videos: nothing can replace proper planning. By proper planning I mean creating project model that takes into account all existing constraints, risks and uncertainties and finding the best possible schedule and required contingency reserves. " 

[PDG] On this point, I disagree with you. The VR and AR videos I am talking about are not done in the past but are designed to show the future.  Imagine the CPM schedule as not being a 2-dimensional piece of paper but a 3-dimensional video showing the workers exactly what work they are supposed to be doing as well as how the work is going to be done?  It is already here now, but in the early stages.  How long will it take to transition from using CPM schedules and replacing it using VR and AR?   Just a guess but I would say 5-10 years.  5 years for complex projects like Offshore platforms and within 10 years, it will be mainstream.  This is where we are right now https://www.youtube.com/watch?v=acLSbNxUP3s and we are now going to see more and more of this in the coming years.

 

BR,

Dr. PDG, Jakarta, Indonesia

 

Zoltan Palffy
User offline. Last seen 3 days 14 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

Anoon thank you for your response and I agree that there will ALWAYS be out of sequence progress that should be corrected.  

Zoltan Palffy
User offline. Last seen 3 days 14 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

Anoon thank you for your response and I agree that there will ALWAYS be out of sequence progress that should be corrected.  

Anoon Iimos
User offline. Last seen 2 years 10 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
Zoltan, with all due respect, I never said that I'm correct, but I'm always looking for the best or the most practical and reasonable solution to the subject issue and I hope you won't mind. And let me reiterate my stand that I'm with you to insist on using "retained logic only" for "Baseline Schedule" (AND/BUT ONLY FOR BASELINE SCHEDULE). However, for current, actual or working schedule, for me, it is better to be flexible. Which means that it must be necessary to reflect always the real or actual situation on your schedule, which you can never achieve if you are going to insist on using only retained logic. I for one believe that you are able to use P6 more than anybody here in PP (Honestly, I knew somebody much better than you, who was also an active member here before but I won't mention). As Dr. Paul said, that P6 and MSP users (sorry Spider, you were not included here), were only using around 10% of the functions of the software, but again, I for one believe that you were using much more than that (Perhaps around 11.5% for you). Anyway, if you insist on using retained logic only on all schedules, then it simply means that you never trusted the people on the grounds, or the ones who got their boots or safety shoes soiled all the time. And of course in return, they will never follow your schedule (in fact they never did). And therefore, you will be having out of sequence schedules all or every time. Best regards, Anoon Iimos (always available should you need assistance)
Zoltan Palffy
User offline. Last seen 3 days 14 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

I wonder why most of the scheduling specifications prohibit the use of progress over ride ?. I guess they are all wrong and Anoon is correct go ahead and use it what could it hurt ? Then you can say HOUSTON WE GOT A PROBLEM! after you use progress over ride.

Dr. Paul,

in your answer to Rafael you discussed Spider Project and the reasons why it is not widely used.

For your information: Spider Project is used by most construction companies in Russia, in most large scale programs (like preparation of 2014 Winter Olympic Games) and was recognized as the best analytical tool for construction industry by Russsian Government Analytical Center. It is also used in all other industries (aerospace, railways, mining, shipbuilding, etc.).

It has customers in 35 other countries but they are few for many reasons:

1) At the conferences where I participated many people told me that they are impressed by Spider Project but their contracts require to use P6 and they do not have an opportunity to select the tool to be used. One person told me that his management explained him that since their company is involved in Government contracts they shall use only American software. So there are certain barriers that do not permit to select the software for construction management.

2) In Russia construction managers frequently asked me the same question:

Why managers in the West use tools that do not plan and manage volumes of work to be done, do not consider resource production rates, are not able to create and apply corporate norms, do not model project budget, use only one WBS, etc.

What shall I answer? The main reason was mentioned in your post: "I only use the CPM schedule as a guide and nothing more."

It does not matter what tool to use for creating CPM schedule that is not resource and cost loaded and used as a guide.

And you are right - most planners do not create project models that can be used for real management amd decision making, they create guides that may be used for contract management and for nothing else. The culture of planning is poor and declines if to compare with planning in early 90-s.

3) We never advertised Spider Project. The quality of the sofware is so high that it very soon became most popular in Russia by the word of mouth. It looks like this model (happy customers tell others) does not work abroad. It looks like software to be used is selected not by those who will actually work with selected tool.

_________________________________________________________________________

And about multiple WBS - as you know Spider Project permits to use multiple WBS since its launch in 1993. The number of different structures is not limited. This feature is always used by Spider customers for more that 25 years.

As for videos: nothing can replace proper planning. By proper planning I mean creating project model that takes into account all existing constraints, risks and uncertainties and finding the best possible schedule and required contingency reserves.

Best Regards,

VL

Anoon Iimos
User offline. Last seen 2 years 10 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
Dr. PDG, While I enjoy the videos (especially Mr. Bean), I think it will still be a long way to go. And I guess Rafael is just happy being a critic and behind him were laymen of over 3 billion people living in the planet. The 1,000 experts who made the compromise of course were entitled to their own opinion. As you know, even without that virtual equipment that you had linked, experience builders can always imagine the works by just closing their eyes. So what if you had that sophisticated equipment? Will it help to assign appropriate human or technical resources? And for sure it will always be a safety issue on site. Imagine having your workers covering their eyes with such equipment on site? Isn't it a chaos? Just allow me to be an annoying critic. Anoon
Paul Giamalvo
User offline. Last seen 2 years 38 weeks ago. Offline
Joined: 14 Feb 2011
Posts: 67

PS Rafael, with the advent of Building Information Modeling, the days of a single dimension WBS/CBS structure are GONE.   Since the mid-1950s, CSI has been publishing a two dimensional WBS/CBS (Uniformat and Masterformat) and about 25 years ago, the Norwegians developed a 3-dimensional WBS/CBS model with Norzok Z-014 and now we have a 15 dimensional model with Omniclass.

 

I have co-authored a book on the subject which should be available in May/June time frame and shows how using these coding structures are essential to enable the 3D, 4D, 5D, 6D and 7D BIM databases to exchange data.    And how this data is going to eventually replace the CPM schedule with the ability to "construct" the project using Virtual Reality or Augmented Reality.

 

Bottom line- what you or I THINK doesn't much matter.  This is where we are heading-  

  1. https://www.youtube.com/watch?v=tAmImhdWYjA 
  2. https://www.youtube.com/watch?v=gF8H_GAm8mM
  3. https://www.youtube.com/watch?v=pPdhLfI7LeM

And sooner or later (probably within our lifetimes) it is going to make CPM scheduling obsolete.

 

BR,

Dr. PDG, Jakarta

Paul Giamalvo
User offline. Last seen 2 years 38 weeks ago. Offline
Joined: 14 Feb 2011
Posts: 67

Raphael, I am not surprised you disagree with the GAO's "Best Practices" as you and I disagree on a lot of issues and the GAO's best practices represented a COMPROMISE by about 1,000 people in total, including some of the most respected and well-known names in the industry.

 

So while I believe NONE of us agrees 100% with that the GAO advocated, there was enough consensus that we could accept compromises.

 

One of the big issues is the fact that while I agree that Spyder software truly is innovative and offers many unique features, the question still remains why it has not been more widely adopted by either owner or contractor organizations?  That is the question you really need answers to as the program has been around long enough and has gotten exposure to enough practitioners that IF we really saw value in using some of those features. then we would be using it.  

 

My take on why Spyder is not more popular is that most people do not even use 10% of the features in MSP or P6, so if they are ignoring 90% of the features in these software packages. maybe they really don't need or want the additional features in Spyder?  I know as a Field guy, I only use the CPM schedule as a guide and nothing more. What is it Dwight Eisenhower told us?  "Plans are useless but planning is essential"?  That is how I see CPM schedules on projects where my own money is on the line if the project succeeds or fails.

 

Bottom line- there is no reason why you cannot or should not volunteer to add your name to the development and evaluation team and then you too can add your "two cents" worth and then make the case why your approach is "better" than what others advocate.

 

BR,

Dr. PDG, Jakarta, Indonesia 

 

Anoon Iimos
User offline. Last seen 2 years 10 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
Rafael, Japanese contractors just follow any standards set internationally, and they have this instinctive discipline that they even require all office workers (site office) to do physical exercise (stretching), first 10 minutes in the morning before starting any work. While I guess Chinese contractors are very different as they always have their own way of doing things (if not just usually copied from others).
Rafael Davila
User offline. Last seen 5 hours 44 min ago. Offline
Joined: 1 Mar 2004
Posts: 5229

Anoon,

Unfortunately the Chinese as well as the Japanese are missing in PP and literature is hard to find.

Best Regards,

Rafael

Anoon Iimos
User offline. Last seen 2 years 10 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
Rafael, for sure you knew that perhaps the top 4 or 5 biggest construction companies in the world today are all Chinese companies. Do you have any idea on what standards and or references for scheduling these companies were using? Should they got their very own way, then I guess these were never discussed here in PP.
Rafael Davila
User offline. Last seen 5 hours 44 min ago. Offline
Joined: 1 Mar 2004
Posts: 5229

Please be warned that the CAO Schedule Assessment Guide is misleading with regard to some important issues.

GAO schedule assesment guide is wrong from Rafael Davila

Because of the reasons stated above on why Monte Carlo simulations can misled it can be argued that the precision of Monte Carlo models is less than that of the 3 scenarios approach.  

It is unbelievable how little is said about schedule trends, there is no guidance at all on how to deal with trends; this is bad, very bad.

Anoon Iimos
User offline. Last seen 2 years 10 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
Dr. PDG, LOL... I'm actually a civil engineer in my country, but I'm never a member of any professional and international organization, nor I got any certificate from PMI, AACEI or whatever. I had my first experience in construction when I was about 11 or 12 years old. And currently I'm unemployed, so this is a real life out of sequence LOL... Best,regards
Paul Giamalvo
User offline. Last seen 2 years 38 weeks ago. Offline
Joined: 14 Feb 2011
Posts: 67

Anoon, there IS a very ROBUST "quality check for schedules".  (Which you would know if you read the GPCCaR ;-) )  This was developed JOINTLY with inputs from PMI, AACE along with other professional groups and about 1,000 other global practitioners and government agencies.

 

Go HERE https://www.gao.gov/assets/680/674404.pdf and download the GAO's Schedule Assessment Guide- "best tested and proven" practice.  Then turn to Appendix 2 and you have an outstanding "Quality Checklist".

 

 

Then go HERE and you can see how some of my graduate level students have used this document as a "quality check" on the schedules submitted to them by contractors-

  1. https://pmworldjournal.net/article/scoring-model-scheduling/
  2. https://pmworldjournal.net/article/assessing-contractor-schedules-in-oman-against-the-gaos-scheduling-best-practice-guide/
  3. https://pmworldjournal.net/article/benchmarking-reported-schedules/

Enjoy...

 

BR,

Dr. PDG, Jakarta

Paul Giamalvo
User offline. Last seen 2 years 38 weeks ago. Offline
Joined: 14 Feb 2011
Posts: 67

And Anoon,

1) I an not an academic but a "hands-on" practitioner with a Ph.D.  I came up through the trades from carpenter apprentice to journeyman, master carpenter, and master builder while earning my degrees part-time at night while working during the day.  When I speak or write, it is based on having done projects where my own money is on the line if the project "succeeds" or "fails".

 

2) What we do is NOT a profession.  My profession is Civil Engineering.  As a construction project manager, I apply the PROCESSES associated with "project management" and "project controls" as the basis to earn my living.  But that alone does not make what we do a profession.  (For more on the processes, visit the GPCCaR- http://www.planningplanet.com/guild/GPCCAR-modules

 

3) Having visited both the Great Wall and the Pyramids of Giza on several occasions, and having studied them over the years, I can almost guaranty you that at some point in time, that they had "out of sequence progress."  They are called "workarounds" or "Plan B" and are almost always the result of some unknown or unanticipated risk event.  And while I recognize there was no P6 or MSP or MicroPlanner around, there is no question there was a plan.  How can I surmise this? Because both the Great Wall and the Pyramids were built according to the seasons and there is written records showing that the Great Wall bankrupted not one but SEVERAL dynasties, indicating the project was over budget and more probably than not, late.

 

Bottom line- based on what you've written, I think your "layman's approach" to scheduling, although quite a common practice,  is seriously flawed, and can only urge you to look over the Guild's CaR to see "best tested and proven" practices researched from around the world.

 

BR,

Dr. PDG, Jakarta

 

Anoon Iimos
User offline. Last seen 2 years 10 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
It is important to consider that even prior to any update, a certain schedule may or is already "out-of-sequence" (as planned), without the planner or scheduler knowing it. As there is no quality control performed or quality assurance for scheduling. Hence, the so-called scheduler's head perhaps grew bigger than the ceiling, and thinking that the schedule will rule the site, and further aggravating the problem during the very first update, especially when insisting on using retained logic only. Further, it is always a fact that the best planners are the ones who actually do the works (corresponding to their respective disciplines or specialties or fortes). Therefore, should there be no inputs coming from this people during the preparation of the schedule, then expect that your schedule will never be followed on site (100%). Remember, the site has always Safety (safety first), Quality Control and Assurance considerations while your schedule has none or have nothing but only stupid logics. Oh I'm sorry Dr. PDG, we were posting at the same time. Yes I agree with you, but reality in most construction projects is not like that (at least from my own experience working on at least seven different countries for various construction projects for more than a dozen companies), but if you were able to see me personally, you might suggest that I'm only 29 years old. Anyway (kidding aside), preparation or development of an overall schedule alone is practically impossible to achieve, considering multi contractor environment or project, multi nationality, multi-culture etc. etc. But in the end, the GC or EPC Contractor must come up with something that must be called a "Master Schedule", no matter what, if it is out of sequence or whatever, otherwise, the GC will lose by default. And for me, this is always a fact. Best regards.
Paul Giamalvo
User offline. Last seen 2 years 38 weeks ago. Offline
Joined: 14 Feb 2011
Posts: 67

Hi Anoon,

I think you missed my point.  My issue is with this statement "And secondly, of course you cannot expect that the scheduler who prepared the schedule knows how to update the schedule properly."

 

The way I did scheduling as a general contractor for 20+ years and how I teach it now was the scheduler did NOT create the schedule.  The people who created the schedule are the people doing the work, with the scheduler only capturing their work flow into the computer and the progress is collected and submitted by the field to the scheduler, who is only responsible to UPDATE the schedule, analyze the results and report back with suggestions/recommendations.  To illustrate how successful this approach is, here is one of the "success stories" from our client- https://pmworldjournal.net/article/earned-value-management-adapted-for-use-in-underground-mining-operations/ who was able to demonstrate savings of 6 million dollars over a 4 year period, and the company is still using this Excel-based method today, some 15 years later.

 

The realities in the field dictate that there WILL be out of sequence progress and instead of second-guessing why the people in the field didn't follow their own plan, the burden is on the scheduler project controls team to find out WHY they deviated, capture the lessons learned then update the schedule to reflect as close as humanly possible what ACTUALLY happened on the project (comes in really handy in the case of claims or litigation) and then show as close as humanly possible, what the ACTUAL FUTURE work plan is.

 

Much of what you have written seems to contradict this basic philosophy, which is one of the reasons why, IMPO, project controls/schedulers are so despised and mistrusted by the field.

 

BR,

Dr. PDG, Jakarta

 

Anoon Iimos
User offline. Last seen 2 years 10 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
Vladimir, Exactly, but even SS+lag or FF+lag nor FS only (by Mike T. only), will never solve the problem of out of sequence. Activity relationships like human relationships is a mystery wherein you need to be flexible in order to capture the actual or real situation, so for me, it is wrong to insist on using "Retained Logic" only on schedules. Even human relationships need to divorce sometimes, and nowadays, people with the same sex are also getting married. Oh excuse me, nature is calling....

If tighter logic (not FS but SS+Lag and FF+Lag) is acceptable then it should be used from the very beginning.

Activity dependencies shall reflect real life constraints and not the way we plan to do the work.

So Zoltan's example shows the case where out of sequence showed that the schedule shall be improved and out of sequence was caused by poor modelling of the real life constraints.

Anoon Iimos
User offline. Last seen 2 years 10 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
Like the example given by Zoltan (and insisting that he's always right). As you can see, Zoltan hangs the wall on electrical rough-ins. Dry walls or gypsum boards maybe are fire resistant, but in case you had screwed the walls directly on the electrical conduits and damaged the wiring inside, then I guess you need to call: HOUSTON WE GOT A PROBLEM!
Rafael Davila
User offline. Last seen 5 hours 44 min ago. Offline
Joined: 1 Mar 2004
Posts: 5229

Vladimir,

Yes Resource Overloads Report gets it right, not so the Overloads Bar.  Maybe the Overloads Bar shall be discontinued in favor of the more reliable report.

Resource-Overloads-Report

Possibly adding Workload field to this report would help to uncover a possible source of updating errors.

I wonder how P6 users would deal with unplanned partial workloads for work done as well as remaining.

Best Regards,

Rafael

Anoon Iimos
User offline. Last seen 2 years 10 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
Dr. PDG, I personally think that the problem of out of sequence really aggravates when firstly, the schedule has incomplete details, meaning - cannot be practically followed on site. And secondly, of course you cannot expect that the scheduler who prepared the schedule knows how to update the schedule properly. As you had stated in your example: a door jamb needs to be properly plumbed before you can proceed with further installation, but if that activity (pertaining to alignment) is not included in the schedule then for sure your schedule will go out of sequence during the update. As you know, builders or people on site never do shortcuts, plus there will always be quality control to check the works, otherwise, it will be rejected. Unlike schedules that were usually done in the office by so-called schedulers whom as you've said may never have seen how real construction is done. And who's doing quality control works for schedules by the way?

Yes Rafael, it happens usually when people entered revised actual dates and duration without adjusting resource usage.

Resource reports show periods of resource overloads and entered numbers of resources working simultaneously at any moment. So it is easy to find and to fix wrong data if required.

Rafael Davila
User offline. Last seen 5 hours 44 min ago. Offline
Joined: 1 Mar 2004
Posts: 5229

Vladimir,

Same as broken date constraints, broken resource constraints can be interesting, even when not identified as such by the software.

Broken-Resource-Constraints

  • Perhaps there was no such overload but wrong updating if using wrong workloads but still OOS events.  
  • In any case it is good to know OOS [+ OOS type] happened.

Resource-OOS-02

Zoltan Palffy
User offline. Last seen 3 days 14 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

here are the differences and why not to use it 

6539
override.jpg

Rafael Davila
User offline. Last seen 5 hours 44 min ago. Offline
Joined: 1 Mar 2004
Posts: 5229

Vladimir,

If I got it right this means some OOS events will never be reported by P6 in any update such as when the OOS events happened in between start and finish of the reporting period.

Broken-Links-in-between-updates

I find Ron_Winter's paper one of the best, and perhaps the best article on OOS ever.  I like his inclusion of broken date constraints as OOS events, irrespectively of what action you decide to take it is valuable to be aware of all broken constraints, knowledge is power.

Because not all OOS events shall be treated equal but in a case by case basis this is another point in favor of the 3 scenarios approach over Monte Carlo.

Best Regards,

Rafael

Anoon Iimos
User offline. Last seen 2 years 10 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
Vladimir, I suspect simply because "out-of-sequence" do not exist in the past or in reality, as it was just derived from a plan or imagination that did not exactly, but diversely realized, but once an activity or related activities have been completed, then how can you see any traces of out of sequence? Perhaps as recorded in your schedule, but who cares anymore when an activity or group of activities have been completed? What's important now is beyond (or at the right) of your data date. Say for example, one or ten workers of the pyramids have been beheaded for pulling one of the stones in opposite direction (and sure what they've done is out of sequence), will you report the beheadings to the emperor if you were the site manager at the time? Knowing that yourself will also be beheaded should the emperor knew that your men have done out of sequence? What do you think Dr. PDG?

Rafael,

I expect that P6 looks for ongoing activities only ignoring out of sequence events in the past.

Anoon Iimos
User offline. Last seen 2 years 10 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
Dr. PDG, Thanks, as I've said I'm just a layman or just an audience who happened to be very interested in planning and scheduling. So I don't care about "Best Practices" and "recommendations and conclusions" from so-called experts. I just found them very entertaining and at the same time very irritating (sometimes), and it stimulates my system which I guess good for the human health (I presumed you were not a medical doctor). Anyway, I cannot agree more with your statements, and I consider it a blessing that there are enthusiastic people from the academic world (like you) who perhaps seriously considers "Project Controls" as a distinguished profession. Now going back to the subject, if perhaps we were able to speak to the geniuses who built the Pyramids or The Great Wall and ask them about "Out-of-Sequence Activities", perhaps those geniuses might thought that why the current human race doing construction works are so stupid given with sophisticated equipment and software and worry a lot about what they called out of sequence activities? Can you imagine the construction without a crane or any machinery at the time? I'm sure anyone who get out of their rhythm immediately get killed. So how they were able to schedule their works? When I'm sure CPM, retained logic or progress override do not exist at the time.
Paul Giamalvo
User offline. Last seen 2 years 38 weeks ago. Offline
Joined: 14 Feb 2011
Posts: 67

Anoon, your statement "And most of the time (again, if not all the time), contractors or specifically, site engineers and construction foremen do not or never follow an approved schedule or plan (and that's a reality as old as construction). Why? First, let me ask everyone (or all schedulers and planners), have you ever seen a construction foreman on site holding your approved schedule while executing the works?" brings up a really great point.

 

My question BACK at you is "Why is it we in the field never see a "scheduler" coming out to the field and asking us how WE plan on executing the work WE are responsible to do?"  The problem (as you can see from the Guild's CaR,  Module 07.3, Figures 2 and 3  http://www.planningplanet.com/guild/gpccar/identify-capture-schedule-act... is that too many schedulers think they know how the work "should" be done, even though many (MOST??) of them never had any real-life field experience. Explained another way, until you have lugged an 8' X 24' Simonds form 30 feet in a muddy hole, or tried to hang a door in a frame that is out of plumb or wind or done any one of the thousands of tasks that you schedule others to do, you have no right to complain that the "field does not follow your schedules". That is mostly YOUR fault, not the fields.

 

The Guild has identified as a "best tested and proven" practice that the scheduler does not CREATE the CPM schedule nor does he/she OWN the CPM schedule. The CPM schedule is created and owned by the people doing the work.  Our job as "project controls" is to capture what the field wants to do, then FACILITATE them in finding the "best" or "most efficient" sequence, capturing what THEY  (Field) plan on doing then tracking THEIR progress against THEIR plan.

 

Your posting is one of the reasons why "project controls" people (aka "Project Police") are so despised by the field people and why you get garbage inputs from the field.  Project controls is there to SUPPORT the field, not DIRECT the field. 

 

BR,

Dr. PDG, Jakarta, Indonesia 

Paul Giamalvo
User offline. Last seen 2 years 38 weeks ago. Offline
Joined: 14 Feb 2011
Posts: 67

Hi Iyke, 

Here is the paper on Retain vs Over-ride published by one of my students for the GPC- Expert credential-

https://pmworldjournal.net/article/retain-or-override/

 

And here are the 4 other papers Steve Paterson published:

  1. https://pmworldjournal.net/article/comparison-8-common-cost-forecasting-...
  2. https://pmworldjournal.net/article/incentivizing-early-completion-major-...
  3. https://pmworldjournal.net/article/scoring-model-scheduling/
  4. https://pmworldjournal.net/article/best-class-dashboards-oil-gas-projects/

I know some of them got submitted to the Guild as the basis for updates to the CaR but so far, I haven't seen that happen.

 

BR,

Dr. PDG, Jakarta

Anoon Iimos
User offline. Last seen 2 years 10 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
Vladimir, for your question Yes. I read the reference linked by Rafael and Ron's conclusion twice. Two things or statements that I was able to capture are: "Out of Planned Sequence is different from Out of Logic Sequence" - very interesting and I wonder what's the difference (I mean in Ron's mind). The other one is: "CPM Theory combined or applied with real world events or progress would be difficult analyze" (sorry if may not be the exact wordings, but that's how I understand it, and please correct me if I'm wrong). Well, as a layman (never an expert), it is my belief that: "Out of Logic Sequence" would never occur in real world construction, otherwise, it will be simply called "Stupidity". While "Out of Planned Sequence" may happen even 100% percent most of the time (not just one third as per the survey referred by Ron), considering a fully linked schedule. Just glad that the reference did not insist on using "Retained Logic" only.
Rafael Davila
User offline. Last seen 5 hours 44 min ago. Offline
Joined: 1 Mar 2004
Posts: 5229

Vladimir,

Got it, very interesting.

Broken-Constraint

I wonder why the abismal difference with P6.

Software-Reporting-OOS

Thank you.

confused-face-smiley-emoticon

Rafael,

common definition of out of sequence does not exist.

In particular the difference of our definition and definition of Ron Winter:

If there is finish constraint (dependency) and it was satisfied then we do not consider that activity execution was out of sequence even if it was started earlier than planned. Managers may use activity flex and assign less amount of resources to do the job without violation of any logical and other restrictions.

Ron considers this case as out of sequence.

The difference in our numbers in Ron's examples was caused by this particular difference in our approaches.

Rafael Davila
User offline. Last seen 5 hours 44 min ago. Offline
Joined: 1 Mar 2004
Posts: 5229

The quality of contractor's schedule is contractor's responsibility.

Out of sequence jobs in contractor's schedule usually tell that the schedule quality is poor and it shall be revised.

But imagine the following case: you have two contractors that shall do their jobs one after another in each room of the building.

The order matters for the second contractor but not for the first. For the first contractor only resource constraints limit the number of rooms done simultaneously.

If the first contractor starts to do the rooms out of approved order it would be necessary to apply retained logic, isn't it?

Anoon Iimos
User offline. Last seen 2 years 10 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
Vladimir, Ideally yes, but as you know it will be so difficult to do that. Firstly because all projects are time and money constrained, and of course technical expertise if not rare are very expensive as well. And even tools or software for scheduling were even argued in terms of costs without even considering functionalities and end results (and this is a fact regardless how huge a certain project is), especially if your project will be involving multi-specialist subcontractors. Gathering information from various subcontractors alone can become a disaster without yet mentioning interfaces to form an overall or master schedule. So before you knew it, some of your subcontractors were already starting construction works, while perhaps others were still worrying about engineering deliverables. So my question is: How on earth you can be able to develop a fully-linked and reasonably sequenced overall schedule and insist on using only "retained logic"?

Anoon,

I expect that we shall discuss the schedules created by real professionals, not amateurs. We both know that most schedules are poor and do not meet basic requirements. But PP is a forum of professional planners that can help to improve approaches and standards of project scheduling. Best practices are rare but still exist.

Resource loading itself requires detailed scheduling. Let's agree that the schedules that can be used for real management and decision making shall be resource loaded and levelled, approved and accepted by site personnel, and only in this case out of sequence may be considered as a problem.

Anoon Iimos
User offline. Last seen 2 years 10 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
Vladimir, The fact is "schedules" were usually copied from projects to projects and usually prepared by amateurs who were perhaps able to use a software but never had any idea on how real construction is done. You are right, as perhaps they just consider "SCHEDULES" as merely a contract requirement, so for as long as you had complied with the stupid requirements or specifications for scheduling, then you are good to go! So you may wonder why "Field Personnel" never follow your schedules or your schedules always go out of sequence? For example: A certain task is called "Excavate Foundation" (as one task in your schedule). In the field, this one task may multiply to several tasks or even hundreds of tasks. First, you need to survey, stake-out, build batter-boards, prepare the equipment, prepare for safety protection, etc. etc. etc.... For MEP works for buildings for example: How can the site people follow tasks named: First Fix, Second Fix, Final Fix? Now are you still wondering why your schedules go out of sequence and STILL INSIST ON "RETAINED LOGIC"?

Anoon, you are right. It is something we warn about.

If project schedule was created in the office by some 'planner' who did not get the data and approval from site managers, when the schedule is created and used not for resource management but for management of contracts only, it will not become decision making tool.

As we discussed earlier most "planners" do not resource load their schedules, do not level project resources, do not visit construction sites. Then "out of sequence" may usually mean that the schedule is poor and must be improved.

Anoon Iimos
User offline. Last seen 2 years 10 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
Vladimir, Yes, it may happen, but unfortunately I've never seen one. It's common to see field personnel holding shop drawings and perhaps method statements or their very own plans or schedules written on scratch paper or an empty pouch of cigarette. I've even saw one very experienced construction manager giving instructions to site engineers while holding a stick and writing something on the sandy ground and just kick off what he had written afterwards. No traces, just one time instruction and that's it! He rules the site without any glance on the so-called approved schedule. And he always do what he does best and delivers in time or even ahead, without any hassles. So how can you insist on "Retained Logic" when your so-called approved schedule go out-of-sequence? Given with actual progress or data which is different from your schedule or sequencing, but much better and ahead in time for example?

Anoon,

I saw. At the start of the shift construction foreman gets the list of the jobs to be done and planned volumes of work. At the end of the shift he enters actual volumes and presses recalculate button. next foremen gets the list of the jobs to be done, etc. Not everywhere, not often, but still this exists.

For "resource constrained schedules": yes, contractor is interested in doing the work faster, but foremen may select one work instead of another that requires the same resources just because he does not see future consequences that are not obvious.

Anoon Iimos
User offline. Last seen 2 years 10 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
Vladimir, You missed to mention that sometimes contractors were even doing construction works even without a plan or schedule (whether or not approved). And most of the time (again, if not all the time), contractors or specifically, site engineers and construction foremen do not or never follow an approved schedule or plan (and that's a reality as old as construction). Why? First, let me ask everyone (or all schedulers and planners), have you ever seen a construction foreman on site holding your approved schedule while executing the works? Well, for "resource constrained schedules", it is my opinion that a contractor with common sense or let's say smart enough would never intentionally delay a schedule, but shall certainly find ways to generate more profits from the works.

Anoon,

in resource-constrained schedules the choice of the wrong activity competing for the same resources may lead to large delays. We consider this out of sequence and insist on following the optimal order created by the scheduling tool.

Another case is starting the construction before the drawings were approved. This is risky but usual.

If out of initial sequence was analyzed and approved then it is fine. In other case it may create problems that can be avoided.

Anoon Iimos
User offline. Last seen 2 years 10 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
Apologies if I'm personally pissed-off with most (if not all) literatures pertaining to the subject / topic; and making mandatory recommendations presuming that they never make any mistake. Please let me challenge everyone of you to walk through your construction sites (assuming that you know all your planning & scheduling even without looking on print outs or your computer), and pin-point any out-of-sequence activity that you can see and penalize all your field personnel for not following your sequencing-logic (as planned). If you are able to see even one activity that you think is out-of-sequence, then for me, you have all the right to insist on using "Retained Logic" only in All Schedules! And punish all your field personnel and engineers as they are all stupid! Otherwise, if you know the Spanish term "Delicadeza", then I guess you already know what to do.
Anoon Iimos
User offline. Last seen 2 years 10 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
For me, the only difference between "Retained Logic" and "Progress Override" is misconception. "Retained logic" is just an illusion until realized. An illusion that is not corrected or rectified is stupidity or insanity. While "Progress Override" is just one of the tools or means to correct or rectify the schedule (if you know how to use it). Again, "Out-of-Sequence Activities" do not or never happen in actual construction (otherwise, all your site engineers, methods engineers and quality control engineers are stupid). Out-of-sequence activities only happen in your computer or on your schedule (or samples) which is just an illusion in the first place. Actual progress were based on facts!
Zoltan Palffy
User offline. Last seen 3 days 14 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

f you use progess override it will do just that it will not honor the logic and it si possible that activities will be scheduled to be completed sooner than physcially possibel. i.e. I have an example that show drywall finishing PRIOR to stud which is physcially impossible. Also all float values will be incorrect. 

6537
override.jpg

Ali Osama
User offline. Last seen 3 years 50 weeks ago. Offline
Joined: 19 Dec 2017
Posts: 39
Groups: None

Primavera P6 Tutorial: Retained Logic vs Progress Override

Developing project plans in Primavera P6 involves identifying the sequence or network logic in which your activities should occur.  The network logic is strategic in the calculation of a Critical Path Method schedule, which is calculated based upon the activity durations and network logic (predecessor/successor relationships).  The schedule’s early dates are calculated during the “forward” pass and the late dates are calculated during the “backward” pass.  The “optimized” project plan becomes the basis for the “baseline” or target plan, which is utilized for performance measurement.  This blog and Primavera P6 Training tutorial demonstrate the options for calculating the schedule when activities occur “out of sequence” thereby violating the network. 

 

Retained Logic Versus Progress Override

The Primavera P6 Schedule Options dialog box enables users to select between Retained Logic, Progress Override, and Actual Dates to identify how Primavera P6 will schedule progressed activities.  The video below demonstrates both Retained Logic and Progress Override options.

When using Retained Logic, the activity that starts out of sequence cannot finish until it’s predecessor has finished. The remaining duration of the out of sequence activity will be scheduled to begin after the predecessor is scheduled to finish.  Retained Logic respects the network logic.

When scheduling using Progress Override, Primavera P6 ignores the relationship between the activities and schedules any remaining duration of the “out of sequence” activity from the data date.

Download Free PDF

Zoltan Palffy
User offline. Last seen 3 days 14 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

Sent to your email address

Iyke Nwosu
User offline. Last seen 5 years 10 weeks ago. Offline
Joined: 7 Jun 2017
Posts: 6
Groups: None

Dear Zoltan,

Thanks for your contributions. My email addy is in.wenceslause@gmail.com

Best Regards 

Rafael Davila
User offline. Last seen 5 hours 44 min ago. Offline
Joined: 1 Mar 2004
Posts: 5229

Iyke,

How Retained Logic, Actual Dates, and Progress Override Deal With Out-Of-Sequence Progress

  • Ultimately, it’s our recommendation that instead of relying on the Progress Override and Actual Dates options to deal with activities that progress out of sequence, owners should specify the use of the Retained Logic option and require contractors to address activities that progress out of sequence on an activity-by-activity basis as it occurs and to make appropriate changes to the schedule logic to ensure that the project schedule matches the current construction.

This is so true, a no-brainer broken logic can create all sort of schedule problems; unfortunately some owners might insist in hijacking your schedule and will not let you make changes in logic to your update schedules unless approved after a reluctant review.

  • A revised Baseline once approved might represent an implicit change order but not so a schedule update. 
  • Schedule updates are essentially informative and shall always represent your true plan; if there is out-of-sequence logic it is a faulty model that might create calculation errors. 
  • If the update shows you are far from contract target(s) then the owner might require you to submit a recovery schedule.
  • In no way the owner shall prevent you from having your plan.  You are the owner of the means and methods (unless it is a Construction Management Contract) . You have the right to make adjustments to your work plan as need be.
  • Why this happens is a mystery to me, perhaps lack of understanding by the owner, perhaps it is because of claims paranoia, but it happens.

Best Regards,

Rafael

Zoltan Palffy
User offline. Last seen 3 days 14 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

it is exactly as it states. Retained logic when an activity have started RETAINIED LOGIC IGNORES THE ACTUAL START DATE AND LOOKS AT THE REMAINING WORK OF THE PREDECESSOR AND WILL NOT PERMIT THE REMAINING WORK OF ITS SUCCESSOR TO BEGIN UNTIL THE PREDECESSOR HAS BEEN COMPLETED. 

If you use progess override it will do just that it will not honor the logic and it si possible that activities will be scheduled to be completed sooner than physcially possibel. i.e. I have an example that show drywall finishing PRIOR to stud which is physcially impossible. Also all float values will be incorrect. 

If you give me your email address I can send you my write up and example.

Iyke Nwosu
User offline. Last seen 5 years 10 weeks ago. Offline
Joined: 7 Jun 2017
Posts: 6
Groups: None

Dear Dr. Paul.

Thank you for the contribution. Will keep looking out for the post in the Guild.

Wramest Regards.

Engr. Iyke

 

Paul Giamalvo
User offline. Last seen 2 years 38 weeks ago. Offline
Joined: 14 Feb 2011
Posts: 67

Hi Iyke two of my GPC Certification students have been exploring this question and one of them has just completed a paper as part of his Expert application in which did a great job of explainng the impacts on both time and costs (Earned Value)

Not sure when the Guild will post the paper but I am sure it has been submitted.  While you are waiting, you can read some of the research which was posted on their blog-  https://js-pag-cert-2017.com/w08-1_sjp_the-effect-retained-logic-progress-override-ev-calculations/


Bottom line- keep watch for the full paper which is in the peer review process right now....

BR,

Dr. PDG, Jakarta, Indonesia