Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

How do u identify long-lead equipment in your schedule?

6 replies [Last post]
John Drokovic
User offline. Last seen 5 years 27 weeks ago. Offline
Joined: 9 Oct 2009
Posts: 24
Groups: None
I have 3 questions for the well experienced planners/schedulers who have developed integrated EPCM schedules:

1. What is the concept of a long-lead equipment? Is it determined by size, cost or other characteristic?

2. Which equipments are considered as long-leads for oil/gas, mining and power plants projects?

3. How do you identify long-lead and schedule-sensitive materials and equipment in order to put it in your schedule?

Thank you.

Replies

Anning Sofi
User offline. Last seen 5 years 38 weeks ago. Offline
Joined: 22 Jan 2012
Posts: 89
Groups: None

Long lead items are those construction equipment or materials that need to be procured and whose procurement lead time (which includes shop drawings, fabrication, delivery) will lead to a delivery date on site that will impact negatively the installation dates of the programme.

Check with your procurement team, what is the delivery lead time for your construction materials; they may have to look at the procurement costs, the requirements of the client (specifications), mode of delivery (by air, ship, land), what shop drawings  need to be produced before fabrication can take place; there may be actual site dimensions needed.

It is not necessary that it will take months for an item to fall under this category.

Salar Al Zubaidi
User offline. Last seen 1 year 50 weeks ago. Offline
Joined: 10 Apr 2007
Posts: 30
Groups: None
Gents,

I wish you can visit this website to have a very clear of the long lead item.

http://www.planningengineers.org/knowledge/leadtimes.aspx
Mike Testro
User offline. Last seen 5 weeks 3 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418
Hi John

The definition of a "Long Lead" item is any piece of kit that is required to be engaged in the project with a procurement time that is likely to affect the completion date.

In tunnelling the availability of the head shield would probabbly be the most critical.

Before you start planning anything set down on a spreadsheet a list of all the pieces of kit that is required and in the next column put the procurement weeks.

This will show you what are the most likely critical Long Lead Items.

When this data is applied to your programme you will learn which one is critical.

Best regards

Mike Testro.
Shah. HB
User offline. Last seen 19 weeks 50 min ago. Offline
Joined: 25 Nov 2008
Posts: 773
Equipments which you could get in local region of your project location they are classified as short lead items whose order & delivery period is less than a week

Long lead items are those whose order to be placed in other countries ,followed by manufacture period consumes more time after manufacture they do factory acceptance testing then delivery to site through over sea or air freight

there is no standard for minimum production period it depends on your project contracts and material specification
John Drokovic
User offline. Last seen 5 years 27 weeks ago. Offline
Joined: 9 Oct 2009
Posts: 24
Groups: None
Thank Shahul for your reply.

Now I have the following questions:

1. Is there any minimum production period for this? (in order for an equipment to fall under the category of long-lead item)

2. What do you with equipments that are NOT long-lead items (i.e. bulk material)? Do you put them in the schedule or ignore them?

Thank you in advance.
Shah. HB
User offline. Last seen 19 weeks 50 min ago. Offline
Joined: 25 Nov 2008
Posts: 773
Equipment whose production period is long is termed as long lead items

Some of long lead items are
1.chillers
2.Generators
3.Pumps
4.AHU/FCU equipment
5.switchgear and so on

One has to go through specification and conditions of contract to identify the long lead items

In the programme long lead items duration are tailored in to 2 0r more activities
for example
100 days long lead duration for generator to be delivered at site

so you need to split them up

1. for ordering of generator 20 days
2. for manufacture of generator 20 days ( 1st set)
3. for manufacture of generator 20 days ( 2nd set)
4. for delivery of generator 20 days ( 1st set)
5. for delivery of generator 20 days ( 2nd set)
then link them up to installation process