Resources driving activity durations!

Member for

19 years 10 months

Hi Ben



Switch off the resource modelling aspect of the software.



Then the allocated hours will spread over the whole period.



Alertanively there are two sides to duration generation - Hours and Gang size.



The 114d duration can be maintained if you reduce the gang allocation pro rata.



This may result in less than 1 resource allocation.



The best result however is to accept that the 114 day duration has been overestimated and let it stay at 25 days.



If this affects the critical path then you can put in a time risk buffer to fill the gap.



Better still an activity of 114 days is too long anyway so break it up into maneable chunks - no more than 20 days - and resource each section.



Best regards



Mike Testro

Member for

17 years

Cheers everyone,



The reason why the resource budgeted hours was driving the Activity duration was because the Duration Type was set to Time/Units, where it should have been Fixed Duration & Units, this prevents the duration changing when you edit the resouce manhours.



Thanks for all your help!



Thanks Trevor I recieved your message late, but I appreciate your help!!



Regards

Ben Hall

Member for

19 years 11 months

Ben,

I think I can help.

You are in WA, so am I.

You can phone me on 08 92727485, we could meet.