Activity profile

2 replies [Last post]
Catherine Barthelemy
User offline. Last seen 13 years 40 weeks ago. Offline
Joined: 13 Jun 2008
Posts: 23
Any of you clever people know how to stagger an activity with non working periods in between over a stretched amount of time and showing as "staggered" bars on one line on the gant chart. (ie: 1 day re-occurring meeting very month)

Replies

Catherine Barthelemy
User offline. Last seen 13 years 40 weeks ago. Offline
Joined: 13 Jun 2008
Posts: 23
thank you very much Nigel I shall try that.
oh the fun we have!
Nigel Winkley
User offline. Last seen 3 weeks 6 days ago. Offline
Joined: 11 May 2006
Posts: 187
Groups: The GrapeVine
Try creating a special calendar set to one day per month and assigning to that activity, then tick the Neck Bars for Non-Work periods.
Nige