Suretrack

2 replies [Last post]
Ferdinand Ancheta
User offline. Last seen 4 years 44 weeks ago. Offline
Joined: 28 Oct 2007
Posts: 28
Groups: None
If i want to update an activity regarding Percent Complete, can i update at one time only? Say i want to change the Percent complete in the activity form. Does the updating in the activity form will also update the Cost and Resource form as well? Please advise.

Replies

Ferdinand Ancheta
User offline. Last seen 4 years 44 weeks ago. Offline
Joined: 28 Oct 2007
Posts: 28
Groups: None
Samer,

Thanks for the reply. However, am not sure if you referring Percent Expended wherein the percentage of actual cost which has been spent to date. And Percent Complete is the percentage of the activity which is complete. Thus, my query refers to the automatic updating of the percent complete both for the activity and cost form. Unless otherwise let Suretrack to calculate the Percent complete. But my program is applied on a manual updating coz’ i’m controlling the completion dates of each activity based from the availability of our resources and milestones.
Samer Zawaydeh
User offline. Last seen 5 years 9 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Dear Ferdinand,

If your program is linked together correctly, then it should work, yes.

Best,

Samer