long lead delievery items schedule

4 replies [Last post]
bilal tirmizi
User offline. Last seen 5 years 16 weeks ago. Offline
Joined: 13 Dec 2008
Posts: 30
Can anyone please explain the concept of Long lead Delievery items schedule

In developing such a schedule whic things to be considered
what information it shall give
which items shall be considered in developing it
in which format it shall be like in primavera or excel

and if some one has on such schedule , please send me for sample

my email id is bilal_tirmzi@hotmail.com

Replies

bilal tirmizi
User offline. Last seen 5 years 16 weeks ago. Offline
Joined: 13 Dec 2008
Posts: 30
THANKS SAMEER

IT WAS VERY HELPFUL

Samer Zawaydeh
User offline. Last seen 5 years 4 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Dear Bilal,

You will need to review your Electromechanical Contract requirements in particular.

Usually long lead items include systems like:
Lifts
Kitchen & Laundry Equipment
Lighting Fixtures
Low Current systems
HVAC equipment
Fire Fighting Pumps
Generators and Package Units.

If you are importing Finishes works, then you will need to check on the approval, manufacturing, delivery and custom clearing procedures.

It is always advisable to have all the information in one place in order not to forget bits and pieces. So include you long lead items in your Procurement Section in your Main Schedule and link it to Material submittal and to the start of Construction.

Good luck,

Samer
bilal tirmizi
User offline. Last seen 5 years 16 weeks ago. Offline
Joined: 13 Dec 2008
Posts: 30
Thanks Ashutosh
Ashutosh Nema, PMP
User offline. Last seen 11 years 46 weeks ago. Offline
Joined: 24 May 2008
Posts: 40
Groups: None
Dear Bilal,
Most important aspect in Long lead items are the manufacruring time,shipment and custom clearance(if applicable).
You can make this schedule in Excel as a Procurement schedule and put duration from tender preparation to delivery on site+time for inspection in Primavera shedule.
Items related to MEP are mostly the long lead items.

Regards
Ashutosh