Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Small Project

3 replies [Last post]
Azeem Abdul
User offline. Last seen 11 years 32 weeks ago. Offline
Joined: 13 Nov 2008
Posts: 19
Hi Planners

Can any one Plz forward me the sequence of a Small Building Project for an area of 2400 Sq Ft.(60’x40’)From foundation to G+3 including 20 RCC Columns in it.

Thanks U

Replies

Samer Zawaydeh
User offline. Last seen 5 years 8 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Dear Maask,

Before you determine the duration, you need to assign the resources; manpower, material and equipment. Depending on the productivity rates, you will determine the duration.

You will need to talk to your team members for determining the available resources.

Best,

SAmer
Ahmed Khan
User offline. Last seen 15 years 11 weeks ago. Offline
Joined: 3 Dec 2008
Posts: 29
Thank U very much samer,

Could U Plz forward me in detailed with the durations of activities.?

Regards

Maask
Samer Zawaydeh
User offline. Last seen 5 years 8 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Dear Azeem,

The activities are:

1. Excavation
2. Blinding
3. Shuttering for Foundation
4. Reinforcement for Foundation
5. Concreting foundation
6. Reinforcement Vertical Elements (20 columns)
7. Shuttering vertical Elements
8. Concreting vertical Element
8.1 Insulation vertical Elements
9. Fill and compaction up to SOG
10. Blinding for SOG
11. Insulation for Slab on Grade
12. Reinforcement for Slab on Grade
13. Concreting of Slab on Grade
Repeat for each level: G+ L1, L2, L3
14. Reinforcement vertical Elements
15. Shuttering vertical elements
16. Concreting vertical elements
17. Deshuttering vertical elements
18. Shuttering for Slab
19. Reinforcement for Slab
20. Concreting slab.

These are the basic activities, you will need to fill in the blanks as per the Contract requirements.

Let us know if you need more assistance.

Best,

Samer