Why P3 Calculate backwards?

6 replies [Last post]
Angel Cruz
User offline. Last seen 11 weeks 2 days ago. Offline
Joined: 16 May 2010
Points: 16
I encounter some difficulties on my P3 Schedule. P3 calculates backward in some of my the activities. On my Project Overview : Project start on 08FEB10 and Project must finish on 17AUG13.

For example I have an activity having duration of 10 days without any predecessor and succesor. So, P3 usually gives ES 08FEB10 EF 17FEB10, but on my file P3 gives ES 08AUG13 EF 17AUG13.

Is there any problems with my setting?
Why P3 calculate backwards?
How to correct this kind of activities?

Tnx.


Angel

Replies

Angel Cruz
User offline. Last seen 11 weeks 2 days ago. Offline
Joined: 16 May 2010
Points: 16
Yup your correct, there is Float Constraint-Zero Free Float..ALAP

Tnx.
Rodel Marasigan
User offline. Last seen 7 weeks 21 hours ago. Offline
Joined: 25 Oct 2006
Points: 1516
Angel,
Can you check if it has Float constrain. Zero free float have that attitude same as As Late as Possible.
vex zex
User offline. Last seen 2 years 32 weeks ago. Offline
Joined: 7 Jul 2010
Points: 42
hi shahul,

just set the start date at project overview,
Then schedule..level...
U can get what u want
Angel Cruz
User offline. Last seen 11 weeks 2 days ago. Offline
Joined: 16 May 2010
Points: 16
Hi Shahul,

But the activity having no succesor, predecessor and constraint.

Could you please direct me to the similar topic you’ve said. I search the forum but didn’t find it.


Tnx in Advance.
Hi Cruz

It is due to the constraints which shows finish date earlier than start date

I have experianced the same and even the similar topic have been discussed in this forum.You could refer for your reference
Activity may be of ALAP (As Late As Possible) type.
And the schedule may be calculated backward - check scheuling settings.

Market Place

Schedule Comparison Tool for P6 and MS Project. Change Happens. Manage it with Change Inspector
Books and training material available from an internationally recognised publisher and PMI accredited REP. Teach yourself or run your own in-house or public planning courses.
Providing permanent and interim planning related recruitment solutions to a range of contractor and consultancy organisations.
Maxim Recruitment – Recruiting Construction, Engineering & Planning Professionals Worldwide in the Infrastructure, Rail, Building and Property Sectors.
EVA18 is the major UK event for Project Control knowledge, know-how and networking. EVA is a conference organised by a project management practitioner for project practitioners and stakeholders