Why P3 Calculate backwards?
Forum Sponsor
Top Posters
Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts
Yup your correct, there is Float Constraint-Zero Free Float..ALAP
Tnx.
Angel,
Can you check if it has Float constrain. Zero free float have that attitude same as As Late as Possible.
hi shahul,
just set the start date at project overview,
Then schedule..level...
U can get what u want
Hi Shahul,
But the activity having no succesor, predecessor and constraint.
Could you please direct me to the similar topic youve said. I search the forum but didnt find it.
Tnx in Advance.
Hi Cruz
It is due to the constraints which shows finish date earlier than start date
I have experianced the same and even the similar topic have been discussed in this forum.You could refer for your reference
Activity may be of ALAP (As Late As Possible) type.
And the schedule may be calculated backward - check scheuling settings.