PIPING SCHEDULE

4 replies [Last post]
Shaunna Inks
User offline. Last seen 12 years 48 weeks ago. Offline
Joined: 27 Mar 2007
Posts: 5
Hi, experts, ’am new in scheduling, was asked to do detailed schedule on mechanical piping in a refinery, can anyone point me to where I could get a sample work breadown structure on piping? I checked the summary schedule and only shows a 1 line activity mechanical piping installation. can anyone help? I appreciate any info!

Replies

Shaunna Inks
User offline. Last seen 12 years 48 weeks ago. Offline
Joined: 27 Mar 2007
Posts: 5
Hi, Rodel! Salamat!
I will email you the stuff that was given to me, and I don’t know where to start.....
thank you again.
Regards,
Shaunna
Rodel Marasigan
User offline. Last seen 1 day 16 hours ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Hi Shaunna Inks,

For Piping usually track as follows.

Piping Fabrication
1) Handling
2) Prep/ Fit-up of spools
3) Welding/ Jointing
4) NDT
5) Painting (Optional/ it can be site painting)
6) Delivery on Site

Piping Instalation
1) Handling/ Set-up in place
2) Jointing (Welding, Screwed, Bolt-up)
3) Valves/ In-line items installation
4) NDT
5) Support/ Hanger
6) Painting/ Touch-up paint
7) Insulation (Optional)
8) Hydrotest
9) Punch list

Commissioning also required but it should be separate WBS as it has their on task/ activities.

Regards,
Rodel
Shaunna Inks
User offline. Last seen 12 years 48 weeks ago. Offline
Joined: 27 Mar 2007
Posts: 5
Thanks, Anoon, I was just given a list of the piping spools, total and , with engineering dwg fabrication dates, ship dates, rec’d on site... but i need to look at a construction methodology, any samples?. thanks again!
Anoon Iimos
User offline. Last seen 2 years 15 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
check your drawings, specifications and methodologies and apply it