I want to have few planning tips from the forum experts before planning for a passenger terminal building for an international airport.
The building Y Shape is which is divided into three components
1. Deparature Hall.
2. Arrival Hall.
3. Central Concourse.
The central portion is having a Mezzanine floor. The duration of the project is around 480 days. The program is to done for only Finishes and architectural work , i.e structure will be done by other contractor.
The main internal finishing work include blockwork , plaster , External cladding , internal cladding to columns , metal works i.e Gaurds rails fixing etc , MEP works all 2nd fix works , wood works i.e. counters etc, painting , lifts , escalators , screed , tiling both granite , staircase finishes and ceramic tile etc.
The issues l would like to get comments from experts are as follows:
How to safeguard myself from the delay if caused by the Structure contractor?
What will be the testing & commissioning time to be allowed in the program for a passenger terminal building?
What will be my critical activities.
Which area of the building to start first???????
The construction of this building requires so many coordination from other contractors, since many different works are allotted to other contractor?????? How can I safeguard from the delay caused by other works??????
What are the long lead items to be considered for planning terminal building?????
Replies