Level 2 Schedule

3 replies [Last post]
Mary Folsom
User offline. Last seen 6 years 27 weeks ago. Offline
Joined: 13 Jun 2003
Posts: 10
What would your definition of a level 2 schedule?

Replies

Andrew Donlan
User offline. Last seen 15 years 47 weeks ago. Offline
Joined: 22 Apr 2003
Posts: 7
Hi Mary

My response below :

Level 2 : This normally is a Project Integrated Schedule - which includes all work broken down into manageable packages, where responsibility, time, cost and resources are embedded in the detail and interfaces between the work packages and functions identified.(Typically 250-300 activities depending on project size of course!)

Best Regards
Andy
Karim Mounir
User offline. Last seen 9 years 38 weeks ago. Offline
Joined: 5 Apr 2006
Posts: 314
Groups: None
Andrew Podolny
User offline. Last seen 43 weeks 1 day ago. Offline
Joined: 16 Nov 2004
Posts: 130
http://www.hud.gov/offices/cpo/evms/clause.pdf

Check the bottom of page 4.
Regards,
Andrew