Would everyone here use a 3/1 data date for February progress?

No replies
John Reeves
User offline. Last seen 1 week 3 days ago. Offline
Joined: 10 May 2013
Posts: 343
Groups: None

Would everyone here use a 3/1 data date for February progress? (aside from some stated date like the 15th etc.) - this way it would match Feb. cost data etc., I always heard that the data date line was like 8am or whatever starting time.  I assume in theory that could be changed to 5pm or whatever ending time but I have never heard of anyone doing that.  

Rodel Marasigan
User offline. Last seen 3 days 4 hours ago. Offline
Joined: 25 Oct 2006
Posts: 1699

The recommended and standard practice of data date is last working date and time of the reporting cycle.
Ex: Weekly cut-off = every Friday Cut-off at last working time say 5:00PM 
     Bi-weekly cut-off = alternate Friday Cut-off at last working time say 5:00PM
     Monthly cut-off = Last Friday of the Month at last working time say 5:00PM
     Shutdown per shift = Say at every 6:00PM 1st Shift and 6:00AM 2nd Shift