Would everyone here use a 3/1 data date for February progress? (aside from some stated date like the 15th etc.) - this way it would match Feb. cost data etc., I always heard that the data date line was like 8am or whatever starting time. I assume in theory that could be changed to 5pm or whatever ending time but I have never heard of anyone doing that.