Data date: you can use the 1st of month every month, does not matter if falls on Sundays etc correct?

3 replies [Last post]
John Reeves
User offline. Last seen 21 weeks 5 days ago. Offline
Joined: 10 May 2013
Posts: 344
Groups: None

Data date:  you can use the 1st of month every month, does not matter if falls on Sundays etc correct?

Replies

Santosh Bhat
User offline. Last seen 11 weeks 1 day ago. Offline
Joined: 15 Apr 2005
Posts: 381

John it's quite fesible if the contract specifies that the schedule must be updated on a certain day of the month (eg. 28th of each month) that this lands on a weekend. 

John Reeves
User offline. Last seen 21 weeks 5 days ago. Offline
Joined: 10 May 2013
Posts: 344
Groups: None

I am not sure why you would say but, if the activity does not have a Sunday and does not fall on a Sunday there is no issue.  I am just wondering if these is a Sat or Sun data date on a schedule with mainly 5 day calendars.  I cannot think of one.

Santosh Bhat
User offline. Last seen 11 weeks 1 day ago. Offline
Joined: 15 Apr 2005
Posts: 381

yes, but if your activity calendars have Sunday as a non-work day then any activity that would commence on the datadate will not fall on that Sunday.