Application Event Error - How do you correct?

2 replies [Last post]
Kim Forbes
User offline. Last seen 1 year 51 weeks ago. Offline
Joined: 15 Apr 2011
Posts: 8

PRM DBAccess Error: Database Server Error: ORA-12952: The request exceeds the maximum allowed database size of 4 GB
ORA-06512: at "ADMPRM$PM.RT_UDFVALUE_DEL", line 3
ORA-04088: error during execution of trigger 'ADMPRM$PM.RT_UDFVALUE_DEL'

Replies

Rafael Davila
User offline. Last seen 3 weeks 1 day ago. Offline
Joined: 1 Mar 2004
Posts: 5241
Pranab Kumar Deb
User offline. Last seen 4 years 11 weeks ago. Offline
Joined: 23 Jan 2007
Posts: 291

Hi Kim,

You have reached the maximum allowable space in Oracle database. Solution is to move to SQL database.

Thanks,

 

Pranab