Physical % complete for milestone date

1 reply [Last post]
moutaz aldeib
User offline. Last seen 4 years 1 day ago. Offline
Joined: 31 Dec 2003
Posts: 291
Groups: None

Hi Planners

I am updating a schedule and the first activity is start milestone, when I enter the actual start date, the percentage complete does not change to 100% and I tried to fill it manually but it does not work. It works for other activities.

 

Regards,

Muataz

Replies

Zoltan Palffy
User offline. Last seen 16 weeks 2 days ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

in the general tab is the % complete type set to physical

did you check the Started box next to the date ?