Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Physical % complete for milestone date

1 reply [Last post]
moutaz aldeib
User offline. Last seen 2 years 27 weeks ago. Offline
Joined: 31 Dec 2003
Posts: 291
Groups: None

Hi Planners

I am updating a schedule and the first activity is start milestone, when I enter the actual start date, the percentage complete does not change to 100% and I tried to fill it manually but it does not work. It works for other activities.

 

Regards,

Muataz

Replies

Zoltan Palffy
User offline. Last seen 4 weeks 3 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

in the general tab is the % complete type set to physical

did you check the Started box next to the date ?