Importing a Resource Assignment Excel File to P6 Schedule

3 replies [Last post]
khalid alshurafa
User offline. Last seen 3 weeks 4 days ago. Offline
Joined: 9 Dec 2020
Posts: 5
Groups: None

Gents,

After making an excel file export from the schedule, I have tried to import again to the same schedule.

However, when I reached the step at which I should select the project to import for, the screen was empty and didn't give any project to select. Hence, I have tried to do the import from a different user account and to the same project and didnt face this issue, and the issue appeared only at my user account.

Does any one has a solutioin for this

Thanks,

Replies

khalid alshurafa
User offline. Last seen 3 weeks 4 days ago. Offline
Joined: 9 Dec 2020
Posts: 5
Groups: None

Thanks Guys,

It has worked after trying the import at anther EPS to which I have access as lead planner/scheduler.

Regards,

Khalid, 

Zoltan Palffy
User offline. Last seen 17 hours 11 min ago. Offline
Joined: 13 Jul 2009
Posts: 2842
Groups: None

Steven is correct you do nto have the rights to do this

Steven Auld
User offline. Last seen 1 day 12 hours ago. Offline
Joined: 13 Sep 2017
Posts: 114
It may be that you do not have Project Superuser access. This is required for excel import.
Steven