Gents,
After making an excel file export from the schedule, I have tried to import again to the same schedule.
However, when I reached the step at which I should select the project to import for, the screen was empty and didn't give any project to select. Hence, I have tried to do the import from a different user account and to the same project and didnt face this issue, and the issue appeared only at my user account.
Does any one has a solutioin for this
Thanks,