Duration and Hours - Minutes

2 replies [Last post]
Jithin Kambhikanam
User offline. Last seen 5 days 19 hours ago. Offline

Hello All,

 

How would you represent Duration and Hours in Minutes.

 

If you want the duration to be 15 minutes what would we type it in hours 0.15H or the duration is 45 min = 0.45H

 

If we want a resource to work 1/2 an hour would we type 0.30H or if a resource is working for 45 min = 0.45H

 

A little confusing.

 

Thanks

Jithin

Replies

Zoltan Palffy
User offline. Last seen 12 hours 53 min ago. Offline
Joined: 13 Jul 2009
Posts: 2926
Groups: None

go to edit users preference

click on the time units tab

under Unit of time make sure it says hour

under durations format change that to hour

then on the right under decimals make sure that is set to 2 decimals