Resource Creep

1 reply [Last post]
Robert Corran
User offline. Last seen 1 year 20 weeks ago. Offline
Joined: 6 Dec 2003
Posts: 26
Groups: None

We have some programmes in Primavear v 16.2 which when scheduled shows the resource dates outside the book ends of the activity they are assigned to, e.g. and activity could be 1st Jan to 10th Jan, say you claim 50% schedule the prograham on a week it pushes the resoure allocation past the remaining end date of the activity, anybody help with this please