Forum Sponsor:

An innovation in P6 Professional training from RPCuk in partnership with Oracle. All the topics that matter to you in workshops customised to your role and industry.  Now get superior training value when you book our Blended Learning Bundle. Learn more here.

Viewer for .xer, xml and xls schedule files Schedule Reader™Free Trial

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Activity duration changed

2 replies [Last post]
Hamid Tavassoli
User offline. Last seen 5 days 10 hours ago. Offline
Joined: 4 Sep 2013
Posts: 8
Groups: None

Hi Friends

I Have a big issues, actually our activities' duration in the P6 under network is changed when we import our subcontractors updated time schedule.

The funny point is that the file in the P6 stand alone doesn't have any problems and all durations are correct, that's why, we must import our subcontractor's updated time schedule in the standalone version.

the calendar assumption for both are:

1- 7 working days with 10 hours per day working

2- Admin Preference sets for 8 hours per day 

 Please help us because we need to work P6 under network with all project planning team. The big problem is that immediately after import the subcontractor's updated time schedule , duration of all projects in the EPS changed that is disaster.

Thanks for your kind attention.

 

   

 

Replies

Zoltan Palffy
User offline. Last seen 6 hours 23 min ago. Offline
Joined: 13 Jul 2009
Posts: 2333
Groups: None

under Admin preferences the Time Period tab make sure that Allow users to specify the number of work hours for each time period is checked.

it looks like what you have listed are conflicting you are working 10 hours per day but your preferences are set or 8 hours per day.

Santosh Bhat
User offline. Last seen 18 hours 52 min ago. Offline
Joined: 15 Apr 2005
Posts: 204

In the Common database, Under Admin Preferences, is the option "Use assigned Calendar to specifiy the number of work hours for each time period" ticked, or unticked?