Hi Friends
I Have a big issues, actually our activities' duration in the P6 under network is changed when we import our subcontractors updated time schedule.
The funny point is that the file in the P6 stand alone doesn't have any problems and all durations are correct, that's why, we must import our subcontractor's updated time schedule in the standalone version.
the calendar assumption for both are:
1- 7 working days with 10 hours per day working
2- Admin Preference sets for 8 hours per day
Please help us because we need to work P6 under network with all project planning team. The big problem is that immediately after import the subcontractor's updated time schedule , duration of all projects in the EPS changed that is disaster.
Thanks for your kind attention.