Hi there
I have an Engineering design schedule where one of my resources is 100% allocated to the project. We have loaded his hours on his design activities however when he is not busy on specific design deliverables the remainder of his time is dedicated to supervising others and various other admin tasks. My problem is the flexible nature of these "Admin" hours. In a busy month he is unlikely to do much but yet with the uniform spread of any admin hours I add it can show him as overallocated in some months and underallocated in others.
Is there a way to create a resource assignment where only on the one activity it will allocate hours monthly based on the resources remaining available time after all activity assignments are accounted for and his remaining availability is determined?
This impacts our cost forecasting and I havent managed to find another way to handle this.
Any help would be hugely appreciated.
Kind Regards
Christine
Replies