How to display resource usage profile for filtered activities only

2 replies [Last post]
Asish Jayakumar
User offline. Last seen 12 years 2 days ago. Offline
Joined: 5 May 2013
Posts: 5
Groups: None

Hi all,

I am facing a problem.

I have created a programme and filtered some activities using Activity codes.

I want the resource usage profile for the filtered activities alone.

How can this be done?

-AJ

Replies

Arnold Puy
User offline. Last seen 10 years 28 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147

Hi Asish,

You can filter the group of activities using activity codes; however it is not possible to show or filter only the lists of the Resources assigned to those activities displayed while currently showing the “Resource Usage Profile” bottom layout.

I suggest you may use the functionality of “Tracking” which show only those resources assigned to each WBS level.

I hope the above assists you.

Cheers,

Arnold

Asish Jayakumar
User offline. Last seen 12 years 2 days ago. Offline
Joined: 5 May 2013
Posts: 5
Groups: None

I am using Primavera P6 R8.2.

-AJ