Remaining Labor Unit by Week

3 replies [Last post]
Jithin Kambhikanam
User offline. Last seen 43 weeks 4 days ago. Offline
Hello Everyone, Need help on how to get a report on Remaining labour units per week after updating the Schedule. Like, Week 24.3 31.3 7.4 Mason 10 5 6 Regards Jithin

Replies

Zoltan Palffy
User offline. Last seen 4 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

of course it worked 

Jithin Kambhikanam
User offline. Last seen 43 weeks 4 days ago. Offline

Thanks Zoltan,

Did that and it worked. Apart from that I also right clicked on the Resource Spreadsheet and clicked on Spreadsheet Field from which I selected "Remaining Units".

Regards

Jithin

Zoltan Palffy
User offline. Last seen 4 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

view show on bottom resource useage spreadsheet

on the right modify resource usage profile

right click spreadsheet fields remaining units

and make the time scale weeks

or

make sure your time scale is weeks

view show on bottom resource useage profile 

 on the right you rigth click and select resource usage profile options

on the data tab under display select units

and under that select remaining early 

click on the graph tab and at the bottom check calculate average and base on hours per time period

the divide by interval should be 40 is viewiing for weeks.