Forum Sponsor:

Oracle Construction and Engineering (formerly Primavera) is transforming the world by helping organizations plan, build, and operate critical assets with on-premise and cloud-based project portfolio management solutions.  Learn more about Oracle Construction and Engineering...

Viewer for .xer, xml and xls schedule files Schedule Reader™Free Trial

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

WBS not in correct hierarchy order after MSP import

3 replies [Last post]
John Turner
User offline. Last seen 9 weeks 3 days ago. Offline
Joined: 8 Feb 2017
Posts: 4
Groups: None

Hi all,

I am currently collecting vendor plans which are mostly in MSP. I have have saved them as a XML and imported them into P6. However, for some reason the WBS heirarchy is being reordered in P6 which is effecting the activities view.

For example in the WBS it is ordered as 

WBS CodeWBS Name
ABC.2 
ABC.2.2 
ABC.2.1 
ABC.4 
ABC.4.2 
ABC.4.1 
ABC.3 


Obvisouly I can manually do this but it is very time consuming as I'm currently collating 30-40 plans and some will have to be re-imported as I improve the vendor plans. 

I have never run into this before and tried looking at the import template but I can't see anything that might cause this. Also, I have not used my current employers P6 to import XML's before (I have previously used my own), so I'm not sure if it is something they have done that is causing this.

I hope someone can help with this. Thanks in advance.

John

Replies

Zoltan Palffy
User offline. Last seen 9 hours 28 min ago. Offline
Joined: 13 Jul 2009
Posts: 2258
Groups: None

There is  converter if you give me your email I can send you the converter

John Turner
User offline. Last seen 9 weeks 3 days ago. Offline
Joined: 8 Feb 2017
Posts: 4
Groups: None

Unfortunatly I can't. I'm using MSP 2010 and Googling the file type it says it was discontinued in MSP 2000. I don't have the option to save as MPX

Zoltan Palffy
User offline. Last seen 9 hours 28 min ago. Offline
Joined: 13 Jul 2009
Posts: 2258
Groups: None

have you tired importing an MPX file from MSP  ?