Order of activities within WBS

1 reply [Last post]
Kate Nash
User offline. Last seen 12 years 3 weeks ago. Offline
Joined: 20 Jul 2011
Posts: 12
Groups: None

If I have several activities with the same start and finish date, and I am sorting by Start Date, how does P6 determine the order of the activities? It doesn't seem to be alphabetical after start date, is there any way I can change the order of activities which have the same start dates?

Replies

Gary Whitehead
User offline. Last seen 4 years 46 weeks ago. Offline

If start date are the same, P6 will by default order by activity id.

 

to change this go to view > group & sort > sort

Use 'add' to include a second sort rule to be applied when start dates are equal