Updating a MPX file

2 replies [Last post]
Ron Beechey
User offline. Last seen 2 weeks 1 day ago. Offline
Joined: 13 Apr 2016
Posts: 28
Groups: None

I would like to update not add to an MPX file that is already been imported into P6.  The drop-down menu doesn't give me the opportunity to update the existing file.  Is there a way to update the project without replacing it.

Replies

Ron Beechey
User offline. Last seen 2 weeks 1 day ago. Offline
Joined: 13 Apr 2016
Posts: 28
Groups: None

Thanks, I'll do option 2 as I can import the file and then export as a xer and then do the update on the original file

Zoltan Palffy
User offline. Last seen 1 day 17 hours ago. Offline
Joined: 13 Jul 2009
Posts: 2480
Groups: None

option #1

open the project in p6 then you can select ADD to existing 

option #2

if you have p3 or sure track convert the file from msp to either p3 or suretrack

then you can import the p3 project and use the update existing project option