Updating Baseline

1 reply [Last post]
Emma Lang
User offline. Last seen 1 year 37 weeks ago. Offline
Joined: 9 Aug 2016
Posts: 45
Groups: None

I've tried updating a baseline in P6 and even if I change one activity by 5 days I receive the following error message in the log file. Assignment remaining start date cannot be earlier than activity remaining start date. 

Does the baseline not get updated at all if there are errors or will it only not update the activities affected?

I've tried searching for the assignment remaining start date and I can't seem to find it, I don't really fully understand what the error message means. 

Thanks

Replies

Zoltan Palffy
User offline. Last seen 3 days 23 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

if it is a true baseline it should never be updated with progress.

Your problem could be the the PROJECT start date is not earlier enough.