Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

How to calculate the overall Performance % complete from the project sections

1 reply [Last post]
Thabo Letlhake
User offline. Last seen 4 years 4 weeks ago. Offline
Joined: 25 Sep 2016
Posts: 5

Hi All

 

My Project Manager requested that I advise on the sectionals Performance % complete in relation to the project overall Performance % complete. In a lame man terms how each section contribute to the overall Performance % complete, I have put in a dummy resource to roll up the column of Performance % Complete as per the Client request to report on the % complete and I did not assign cost to the activities. Can someone advise how does one workout the propotion of the sections on P6.

 

Thanks

 

K.R

TD Letlhake

Replies

Zoltan Palffy
User offline. Last seen 4 weeks 3 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

you can use project tracker to do this 

https://www.willmer.co.uk/project-tracker

or use the activity $ complete and roll that up and summarize the data