how to asign multiple activities to a wbs?

4 replies [Last post]
Ahmet Tuter
User offline. Last seen 4 years 16 weeks ago. Offline
Joined: 7 Feb 2013
Posts: 52
Groups: None

is there a shortcut to assign multiple new activities i created to a wbs all at once? one by one is taking too much time

Replies

Zoltan Palffy
User offline. Last seen 11 weeks 3 days ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

2 options

option #1

if you can get your activities lined up or group another way then you can add a column for the wbs and then do the 1st one and then do a fill down

option #2

you can export the activites to excel when you export them if they have not been assigned they wil automatically  take the wbs of the project id that is the highest level. You can then change them in excel and import them back into p6

Zahid Rehman
User offline. Last seen 7 years 41 weeks ago. Offline
Joined: 10 Apr 2011
Posts: 13
Groups: GPC Qatar

I was looking for the solution of the same issue since last one week but in vain.... Thanks Chandran , this tip really worked...

Zoltan Palffy
User offline. Last seen 11 weeks 3 days ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

add a column for wbs do the first one then do a fill down 

Rama Chandran
User offline. Last seen 8 years 26 weeks ago. Offline
Joined: 18 Dec 2011
Posts: 10

Select the activities (Ctrl+Activity).

Move the cursor to the left side of the activity table. Cursor with small rectangle appears.

Now drag the activities to the needed WBS.