If an activity has +10 days of total float, which means if we delay this activity by 10 days it becomes critical path. Just to simulate, if we make this activity's duration increased by 11 days. Then this activity would drive the project end date and would be on longest path. This scenario is understood. Based on this, the situation should also true with negative float. That is, if an activity has -30 days of negative float, should this does mean that this activity is pushing out the end date by 30 days ?
In my schedule, I have like -120 days negative float but still the activity is not on critical path. I am struggling to interpret this situation. Please share your thoughts.
P.S : In the schedule, we have imposed an constraint on the finish milestone to map the contractual position. Since the project is delayed, there is a negative float.
Replies